Hammock Activity: Definition, Example and When to Use It

A hammock activity is a summary activity that spans a group of other activities and takes its duration from them. It starts when the first linked activity starts and finishes when the last one finishes, so it stretches or shrinks like a hammock hung between two points.

Key takeaways

  • A hammock spans a group of activities and takes its duration from them.
  • Link it SS from the first activity and FF from the last.
  • Use it for level-of-effort support and time-based costs.
  • It should follow the network, never drive it.

How a hammock activity works

  • It is linked start-to-start to the first activity in the group and finish-to-finish to the last one.
  • Its duration is calculated, not estimated: it equals the time between those two points.
  • If the activities in between slip, the hammock automatically lengthens.
  • It often carries resources or costs that run for the whole period, such as site supervision, equipment hire or project management.

Worked example

Using our standard network (A to F, critical path A-B-D-F, 14 days; see critical path method), the team adds a hammock called Site supervision linked SS to A and FF to F.

ScenarioA startsF finishesHammock durationSupervision cost at $400 a day
PlanDay 0Day 1414 days$5,600
D slips 2 daysDay 0Day 1616 days$6,400
D crashed by 2 daysDay 0Day 1212 days$4,800

Because the hammock follows the network, the cost of time-dependent support updates itself whenever the schedule changes.

Hammock vs summary task

Hammock activitySummary task
Based onDependency links to chosen activitiesThe outline (WBS) hierarchy
Activities coveredCan span activities from different branchesOnly its own child tasks
Can hold resourcesYes, commonlyUsually not recommended
Typical useLevel of effort support across a periodGrouping and rolling up a phase

When to use one

  • Level-of-effort work such as project management, quality assurance or site security.
  • Equipment or facility hire that lasts as long as a set of activities.
  • Summarising a cross-phase stretch for senior reports.
  • Tracking time-related costs in earned value management.

How to create one

  1. Identify the first and last activities the hammock should span.
  2. Create a new activity with no fixed duration.
  3. Link it start-to-start from the first activity and finish-to-finish from the last.
  4. Assign the resources or costs that apply for the whole period.
  5. Check that it recalculates when you change durations upstream. Some tools have a dedicated hammock or level-of-effort activity type.

Free templates for this topic

Browse all templates

Frequently asked questions

What is a hammock activity?

A summary activity whose duration is set by the start of one activity and the finish of another, so it changes automatically when they move.

Why is it called a hammock activity?

Because it hangs between two points in the schedule and stretches or shrinks as they move.

How is the duration of a hammock activity calculated?

It equals the finish of the last linked activity minus the start of the first linked activity.

Is a hammock activity on the critical path?

It is not usually treated as critical because it does not drive any other work, even though it spans critical activities.

What is the difference between a hammock activity and a summary task?

A summary task groups its child tasks in the WBS; a hammock is linked by dependencies and can span any activities.

Is a level-of-effort activity the same as a hammock activity?

Not exactly. A level-of-effort activity is support work, such as project management, that has no specific output and lasts as long as the work it supports. Hammock activities are often used to model it.

Can a hammock activity have resources?

Yes. Assigning time-based resources and costs to a hammock is one of its main uses.

Does Microsoft Project support hammock tasks?

It can be imitated by linking a task's start and finish dates to other tasks. Some other scheduling tools have a built-in hammock type.

Should a hammock activity drive other activities?

No. It should only follow other activities, otherwise you can create circular logic.

How does a hammock activity help with cost control?

Costs that depend on time update when the schedule moves, improving cost control and forecasts.