Agile guide · Getting started with Agile
How to Run an Agile Project: Step-by-Step With Example
To run an Agile project, agree a clear vision, form a small cross-functional team with a Product Owner, build and order a backlog, plan a minimum viable product with a forecast range, then deliver in short sprints and review working results with stakeholders every sprint until you release. This guide takes one project from kickoff to closure in 10 steps, with a sprint calendar, a worked release forecast and an illustrative three-month example. If you are introducing Agile across several teams or a whole organisation, see our guide to implementing Agile instead.
Key takeaways
- An Agile project fixes the team, the time window and the budget, and lets scope flex by value. The Product Owner decides what is built next.
- Start with a one-page vision and a short inception phase, not a detailed plan. You need just enough backlog for the first release.
- Aim for a minimum viable product and forecast it as a range, using the team's velocity, then update the forecast every sprint.
- Run a steady cadence of Sprint Planning, Daily Scrum, Sprint Review and Retrospective, and invite stakeholders to every review.
- Report working output, a burnup chart, the forecast range and the top risks rather than percentage complete.
- Release as soon as the increment is valuable, measure real use, then close the project or hand the product to a continuing team.
What does running an Agile project involve?
Running an Agile project means delivering a product or outcome in short, fixed-length iterations, with a stable team that plans just enough, builds a usable increment every cycle, shows it to stakeholders and adjusts the plan based on what it learns. Scope is ordered by value and can change; the team, the cadence and the quality standard stay fixed.
The table shows how this differs from running the same project in a traditional, plan-driven way.
| Traditional project | Agile project | |
|---|---|---|
| Planning | Detailed plan up front | Vision and release plan up front; detail planned each sprint |
| Scope | Fixed; changes go through change control | Flexible; the Product Owner reorders the backlog |
| Delivery | One delivery near the end | A usable increment every sprint; releases as soon as valuable |
| Progress measure | Tasks complete against the plan | Working output and a forecast range |
| Stakeholder involvement | Mainly at the start and end | At every Sprint Review |
For a fuller comparison, see Agile vs Waterfall. This guide assumes you have the freedom to run one project the Agile way. Read how to implement Agile if you are introducing Agile across teams or a department.
The Agile project lifecycle at a glance
Agile projects still have a beginning, middle and end. The phases below are a practical way to organise them; the sprint phase repeats until the product is ready to release.
| Phase | Purpose | Main outputs | Typical length |
|---|---|---|---|
| Initiate | Confirm the problem, sponsor and fit | Vision, lightweight charter | Days to 2 weeks |
| Inception (Sprint 0) | Align the team, shape the first backlog | Story map, initial backlog, Definition of Done, release forecast | 1–2 weeks |
| Sprints | Deliver and learn in short cycles | Done increments, updated backlog and forecast | Most of the project |
| Release | Put the product in users' hands | Released increment, support plan | Can happen every sprint or at milestones |
| Close or continue | End the project or hand over to a product team | Lessons learned, handover | 1–2 weeks |
Many UK public-sector teams use a similar phased approach called discovery, alpha, beta and live, where discovery tests whether the problem is worth solving and alpha tests possible solutions before building the real service.
Step 1: Check that Agile fits the project
Agile works best when the outcome is clear but the best way to reach it is not, and when users can give feedback on partial results. Use this quick check before you commit.
| Signal | Points to Agile | Points to a predictive or hybrid approach |
|---|---|---|
| Requirements | Likely to change as people see results | Stable and well understood |
| Delivery | Can be split into usable increments | Only useful when complete, such as a building |
| Users | Available to give regular feedback | Not available until acceptance |
| Team | Can be dedicated and stable | People join for short specialist tasks |
| Constraints | Some flexibility in scope | Scope, date and cost all fixed by contract |
Mixed signals usually suggest a hybrid: a predictive plan for fixed parts, such as procurement or installation, and Agile sprints for the parts where learning matters, such as software or service design.
Step 2: Write the vision and a lightweight charter
Before anyone writes a user story, agree why the project exists. A short product vision keeps decisions consistent when priorities change. A simple template:
Add the essentials a sponsor needs to approve the work. Keep it to one or two pages.
- Goal and success measures: what will be different, and how you will measure it, such as online bookings or time saved.
- Constraints: budget, time window, regulations and fixed dates.
- Team and roles: who is the sponsor, Product Owner and team.
- Assumptions and top risks.
- Governance: how often the sponsor sees progress, usually at Sprint Reviews.
Our project charter guide explains each element, and the free Agile project plan template includes a lightweight Agile charter alongside the vision, epics and release plan.
Step 3: Form the team and agree roles
An Agile project team is small, cross-functional and stable. The Scrum Guide describes a Scrum Team of 10 or fewer people, including the Product Owner and Scrum Master, with all the skills needed to create a usable increment each Sprint.
| Role | Accountable for | Time on the project |
|---|---|---|
| Sponsor | Funding, the business case, removing organisational blockers | Attends Sprint Reviews |
| Product Owner | Vision, ordering the backlog, accepting work, stakeholder decisions | Most of their week |
| Scrum Master or Agile lead | The process, coaching, removing impediments | Part- or full-time |
| Developers (all skills) | Building, testing and delivering the increment | Full-time where possible |
| Stakeholders and users | Feedback on increments, domain knowledge | Reviews and workshops |
Where does the project manager fit? On a single Scrum team the project management work is shared out: the Product Owner owns scope and priorities, the team owns delivery and the Scrum Master owns the process. Many organisations keep an Agile project manager to handle budget, contracts, risks, dependencies and reporting, especially on larger or hybrid projects.
Finish by agreeing a team working agreement: core hours, communication channels, how decisions are made and how the team handles urgent requests. See what is an Agile team for more on team design.
Step 4: Hold a kickoff and an inception phase
A kickoff gets everyone on the same page; a short inception phase, often called Sprint 0 or iteration zero, prepares enough to start delivering. The Scrum Guide does not define a Sprint 0, so treat it as a common practice: keep it short, and if it can produce something usable, even a basic working page, do so.
| Session | Who | Output | Typical time |
|---|---|---|---|
| Kickoff: vision, goals, constraints | Sponsor, Product Owner, team, key stakeholders | Shared understanding of why | 2 hours |
| Story-mapping workshop | Product Owner, team, users | Story map and first release slice | Half a day |
| Technical and design spikes | Developers | Approach agreed for the riskiest parts | 1–3 days |
| Definition of Done and working agreement | Team, Product Owner | Agreed quality standard | 1–2 hours |
| Initial estimation | Team | Story points or sizes for the first release | 2–3 hours |
| Board and tools set-up | Scrum Master, team | Board, backlog, dashboards | Half a day |
By the end of inception you should be able to answer: what are we building first, roughly how big is it, what does done mean, and when is the first Sprint Review?
Step 5: Build the backlog with a story map
A story map lays out the user's journey from left to right and the stories that support each step underneath, most important at the top. A horizontal line then marks what goes into the first release. It stops the backlog becoming a flat list of features with no sense of the whole.
Example: a story map for an online class booking service
This example is illustrative.
| Find a class | Book | Pay | Manage booking |
|---|---|---|---|
| Search by day and centre (MVP) | Book a place (MVP) | Pay by card (MVP) | Cancel a booking (MVP) |
| Filter by class type (MVP) | Join a waiting list (release 2) | Use membership credits (release 2) | Email reminder (MVP) |
| Save favourite classes (release 2) | Book for a friend (later) | Pay by gift voucher (later) | Rate a class (later) |
Write stories the team can deliver
Turn each item into a user story with acceptance criteria, for example: "As a member, I want to cancel a booking up to two hours before the class, so that someone else can take my place." Acceptance criteria then state the rules, such as the two-hour cut-off and the confirmation email. See our guide to user stories and the free user story template.
Order the backlog by value, risk and dependencies, put the riskiest learning early, and make sure the top items meet your Definition of Done criteria before you call them finished.
Step 6: Define the MVP and forecast the release
A minimum viable product (MVP) is the smallest version that delivers value to real users and generates learning. Use MoSCoW (Must, Should, Could, Won't this time) to agree the line on the story map with stakeholders, then estimate the items above it.
Worked example: a release forecast
The numbers are illustrative. The MVP backlog is estimated at 120 story points. After the first sprints, the team's velocity ranges from 18 to 24 points per two-week sprint.
| Scenario | Velocity | Calculation | Sprints needed |
|---|---|---|---|
| Optimistic | 24 points | 120 ÷ 24 = 5.0 | 5 sprints (10 weeks) |
| Pessimistic | 18 points | 120 ÷ 18 = 6.7, rounded up | 7 sprints (14 weeks) |
Communicate the forecast as a range: "The MVP is likely to be ready in 10 to 14 weeks." Before the team has any velocity, use a capacity-based estimate and say clearly that the range will narrow after two or three sprints. If stakeholders need a fixed date, fix it and let the scope beneath the MVP line flex instead.
See Agile release planning for release burnup charts and multi-release planning.
Step 7: Run the sprint cycle
Most of the project happens here. A sprint is a fixed period of one month or less, usually two weeks, in which the team turns backlog items into a Done increment. The 2020 Scrum Guide sets maximum timeboxes for a one-month Sprint (Sprint Planning 8 hours, Sprint Review 4 hours, Sprint Retrospective 3 hours); for shorter Sprints the events are usually shorter. The Daily Scrum is 15 minutes.
A typical two-week sprint calendar
| When | Event | Typical length | Purpose |
|---|---|---|---|
| Day 1 morning | Sprint Planning | 2–4 hours | Agree the Sprint Goal and select backlog items |
| Every day | Daily Scrum | 15 minutes | Inspect progress towards the Sprint Goal and adapt the plan |
| Around day 6 | Backlog refinement | 1–2 hours | Clarify and size items for the next sprint |
| Day 10 | Sprint Review | 1–2 hours | Show the increment to stakeholders and update the backlog |
| Day 10 | Sprint Retrospective | 1–1.5 hours | Agree improvements to how the team works |
Protect the Sprint Goal. If something urgent arrives, the Product Owner decides whether it waits for the next sprint or, in rare cases, whether the Sprint Goal is still worth pursuing. For more on how sprints work, see what is a sprint.
Step 8: Manage scope, risks and change
In an Agile project, change is expected, but it still needs managing. The rule is simple: the team's capacity is fixed, so adding something means something else moves down or out.
- New request arrives. It goes to the Product Owner, not straight to a team member.
- Product Owner assesses value against what is already in the backlog and the vision.
- Team sizes it during refinement.
- Product Owner places it in the backlog. If it goes above the release line, an item of similar size moves below it.
- Forecast is updated and the trade-off is explained at the next Sprint Review.
Treat risks the same way. Add risk-reducing work, such as a prototype or a load test, to the backlog and order it early. Keep a simple log of risks, assumptions, issues and dependencies, for example our RAID log template, and review the top items at each Sprint Review.
Larger changes that affect the vision, budget or time window go back to the sponsor. That is a governance decision, not a backlog decision.
Step 9: Report progress to stakeholders
The best report on an Agile project is the working increment at the Sprint Review. Between reviews, a one-page status update is usually enough.
| Include | Why |
|---|---|
| Sprint Goal and whether it was met | Shows focus and reliability |
| What was completed, with a link or demo | Evidence of real progress |
| Release burnup chart | Shows completed work against total scope, including scope changes |
| Forecast range for the next release | Answers when it will be ready, honestly |
| Top three risks or blockers and who owns them | Where stakeholders can help |
| Decisions needed | Keeps the sponsor engaged |
Avoid percentage complete: on an Agile project the total scope changes, so the percentage misleads. A burnup chart shows both lines, completed work and total scope, so everyone can see whether the gap is closing. Our guide to the Agile velocity chart explains how to read the team's delivery trend.
Step 10: Release, measure and close
Release as soon as the increment is valuable, rather than waiting for everything. Before each release, check:
- All items meet the Definition of Done, including testing, accessibility and security checks.
- Users, support and operations teams know what is changing.
- There is a way to measure use, such as analytics or feedback forms, linked to the success measures in the charter.
- There is a rollback or fix plan if something goes wrong.
After release, feed real usage data and feedback back into the backlog. Many Agile products then continue with the same team, and the project simply becomes ongoing product development.
Closing an Agile project
If the project does end, close it deliberately: hold a final retrospective covering the whole project, hand over to the team that will support the product, close budgets and contracts, archive the backlog and share lessons learned. A lessons learned template keeps this short and useful.
Worked example: running a three-month Agile project
This example is illustrative. The organisation, figures and events are invented to show how the steps fit together.
A group of leisure centres wants members to book classes online instead of by phone. The sponsor sets a budget for a team of seven for three months: a Product Owner from the membership team, a Scrum Master and five developers covering design, front-end, back-end and testing. Success means at least half of class bookings made online within three months of launch.
Inception (week 1)
The kickoff agrees the vision. A half-day story-mapping session with two centre managers and four members produces the map shown in step 5. The MVP, covering search, book, pay by card, cancel and reminders, is estimated at 120 points. The deadline allows six two-week sprints.
Sprint by sprint
| Sprint | Velocity | Done so far | What happened |
|---|---|---|---|
| 1 | 16 | 16 / 120 | Search and basic booking work end to end; payment provider set-up takes longer than expected |
| 2 | 22 | 38 / 120 | Card payment live in test; forecast after Sprint 2: 4–6 more sprints, so the deadline is at risk |
| 3 | 24 | 62 / 120 | At the review, centre managers ask for a waiting list (13 points) |
| 4 | 23 | 85 / 120 | Waiting list built; scope changes below take the MVP to 112 points |
| 5 | 21 | 106 / 112 | Accessibility review finds issues; fixes added to the backlog |
| 6 | 14 + fixes | 112 / 112, plus class filter | Last MVP items, accessibility fixes and load test; release |
How the scope change was handled
After Sprint 3, 58 points remained and three sprints were left. Recent velocity of 16–24 points gave a capacity of roughly 48–72 points. Adding the 13-point waiting list made 71 points, close to the optimistic end. The Product Owner moved "email reminder" (13 points) to release 2 and placed "filter by class type" (8 points) below the line as a stretch item, giving 50 points and a realistic plan. The sponsor agreed the trade-off at the Sprint 4 review. Because Sprints 4 and 5 went well, the team also delivered the class filter in Sprint 6.
Outcome
The service launched at the end of week 13. The team stayed together for a further quarter to add email reminders, membership credits and the waiting-list improvements users asked for, so the project closed with a handover to that continuing product team and a project retrospective rather than a disbanded team.
Running an Agile project with a fixed budget or deadline
Most real projects have at least one fixed constraint. Agile handles this by fixing time and cost and letting scope flex, which is the opposite of the traditional triangle where scope is fixed and time and cost absorb the changes.
| Constraint | What stays fixed | What flexes | How to manage it |
|---|---|---|---|
| Fixed budget | Team size and number of sprints | Scope below the MVP line | Order by value so the most important items are done first |
| Fixed deadline | Release date | Scope below the MVP line | Forecast every sprint; move items early, not in the last week |
| Fixed scope | Must-have features | Date and cost | Use a predictive or hybrid plan; still deliver incrementally |
| Fixed price contract | Price and outcome | Detailed features within an agreed scope | Agree a swap rule: new items replace items of equal size |
Whatever is fixed, make the MVP smaller than the full capacity, so the project has a buffer for surprises.
Common mistakes when running an Agile project
- Skipping the vision. Without it the backlog becomes a list of requests with no way to choose between them.
- A Product Owner with no time or authority. Decisions stall and the team guesses.
- Too long an inception. Weeks of analysis before any delivery is a waterfall phase with a new name.
- Promising a single date. Give a range and narrow it as velocity becomes reliable.
- Adding work mid-sprint. It breaks the Sprint Goal and makes velocity meaningless.
- Reporting percentage complete. Use burnup charts and working output.
- Treating the Sprint Review as a demo only. Its purpose is to decide what to change next.
- Leaving testing and release tasks to the end. Build them into the Definition of Done from the start.
Tools for running an Agile project
For a small co-located team, a physical board and a spreadsheet backlog can be enough. Most teams use a digital tool for the board, backlog, burnup chart and stakeholder visibility.
- Jira has mature Scrum and Kanban boards, backlogs and sprint reports, and is a strong choice for software projects.
- Wrike, our top-rated tool, works well for cross-functional Agile projects that combine sprints with request intake, dashboards for sponsors and reporting across several projects.
- monday.com and ClickUp offer flexible boards and sprint features that non-technical teams find easy to adopt.
Whatever tool you choose, start from the Agile project plan template and the release plan template to agree the vision, epics and forecast before you configure the tool.
Free templates for this topic
Frequently asked questions
What are the steps to run an Agile project?
Check Agile fits, write the vision and a light charter, form the team, hold a kickoff and short inception, build the backlog with a story map, define the MVP and forecast it, run sprints, manage scope and risk through the backlog, report with working output and burnup charts, then release, measure and close or continue.
How do you start an Agile project with no backlog?
Run a story-mapping workshop with users and stakeholders. Lay out the user journey, list the stories under each step, draw a line for the first release and write user stories with acceptance criteria for the items above it.
Who manages an Agile project?
Management is shared. The Product Owner owns scope and priorities, the team owns delivery and the Scrum Master owns the process. Many organisations also use an Agile project manager for budget, contracts, risks and dependencies.
What is Sprint 0 in an Agile project?
A short preparation period, usually one or two weeks, used to align the team, build the first backlog, agree the Definition of Done and set up tools. It is a common practice rather than part of the Scrum Guide.
How long should sprints be in an Agile project?
One month or less under the Scrum Guide. Two weeks is the most common choice because it gives frequent feedback without too much planning overhead. Keep the length consistent once chosen.
How do you forecast how long an Agile project will take?
Divide the remaining backlog estimate by the team's lowest and highest recent velocity to get a range of sprints, then update it every sprint. See Agile release planning.
How do you report on an Agile project?
Show the working increment at Sprint Reviews and share a short update with the Sprint Goal result, a release burnup chart, the forecast range, top risks and decisions needed. Avoid percentage complete.
Can you run an Agile project with a fixed budget?
Yes. Fix the team and the number of sprints, order the backlog by value and let lower-priority scope flex so the most valuable features are delivered within the budget.
How do you handle scope changes in an Agile project?
New requests go to the Product Owner, who weighs them against the backlog. If a new item goes above the release line, an item of similar size moves below it, and the forecast is updated at the next Sprint Review.
What documents does an Agile project need?
Usually a product vision, a lightweight charter, an ordered backlog with user stories, a Definition of Done, a release plan with a forecast range, a risk or RAID log and short status updates. Add whatever your governance or regulations genuinely require.
How do you close an Agile project?
Hold a final project retrospective, hand over to the team supporting the product, close budgets and contracts, archive the backlog and share lessons learned. Many Agile products continue with the same team instead.
Can a non-software project be run with Agile?
Yes, if the work can be split into increments that people can review, such as marketing campaigns, service designs or process changes. Projects that are only useful when complete often suit a hybrid approach.