Scrum guide · Artifacts and practices
Product Backlog: What It Is and How to Manage It in Scrum
The product backlog is an emergent, ordered list of what is needed to improve a product, and the single source of work for the Scrum Team. The Product Owner is accountable for it, and its commitment is the Product Goal. This guide explains what the Scrum Guide says, what goes into a backlog, and how to build, order and refine one step by step, with worked examples, prioritisation techniques and the mistakes to avoid.
Key takeaways
- The product backlog is an emergent, ordered list and the single source of work for the Scrum Team. There is one backlog per product.
- Its commitment is the Product Goal: a future state of the product that the team plans against, one goal at a time.
- The Product Owner is accountable for the content and order; the Developers who will do the work size the items.
- Items near the top are small, clear and ready for Sprint Planning; items lower down stay coarse until they are needed.
- Order by value, risk, dependencies and learning, using techniques such as MoSCoW or WSJF as inputs, not as a replacement for judgement.
- Keep the backlog healthy: refine continuously, delete items that no longer serve the Product Goal and avoid a list that only grows.
What is a product backlog?
A product backlog is an ordered list of everything the Scrum Team currently believes is needed to improve a product: features, fixes, technical work, research and experiments. The 2020 Scrum Guide calls it "an emergent, ordered list of what is needed to improve the product" and the single source of work undertaken by the Scrum Team.
The product backlog is one of the three Scrum artifacts, alongside the Sprint Backlog and the Increment. Each artifact has a commitment that gives it focus; for the product backlog, that commitment is the Product Goal.
Four characteristics set it apart from an ordinary to-do list:
- Emergent. It is never complete. Items are added, changed, split and removed as the team, users and stakeholders learn.
- Ordered. Every item has a position relative to every other item, so everyone can see what comes next.
- The single source of work. If the Scrum Team is going to work on something, it should be visible in the product backlog, not hidden in emails or side lists.
- One per product. Several Scrum Teams working on the same product share one product backlog and one Product Owner.
What the Scrum Guide says about the product backlog
The Scrum Guide is short, and it says less about the product backlog than many people assume. The 2020 edition is still the current official version (checked 25 October 2026). The table summarises its main points and what each one means in practice.
| The Scrum Guide says | What it means for your team |
|---|---|
| An emergent, ordered list of what is needed to improve the product | Expect constant change, and keep one clear sequence rather than a pile of labels |
| The single source of work undertaken by the Scrum Team | Work outside the backlog is invisible; bring it in |
| Its commitment is the Product Goal | Every item should help reach the current Product Goal, or be questioned |
| Refinement breaks items down and adds detail such as a description, order and size | Refinement is an ongoing activity, not a formal Scrum event |
| The Developers who will be doing the work are responsible for the sizing | The Product Owner can explain trade-offs but should not dictate estimates |
| Items that can be Done within one Sprint are deemed ready for selection in Sprint Planning | Large items must be split before they are pulled into a Sprint |
| Those wanting to change the backlog do so by trying to convince the Product Owner | Stakeholders influence the order through the Product Owner, not around them |
| Teams on the same product share one Product Goal, Product Backlog and Product Owner | No separate competing backlogs for one product |
Notice what is missing: the Scrum Guide does not require user stories, story points, epics, a Definition of Ready or any prioritisation technique. These are optional complementary practices.
The Product Goal
The Product Goal describes a future state of the product that the Scrum Team plans against. According to the Scrum Guide it is the long-term objective for the Scrum Team, it sits in the product backlog, and the rest of the backlog emerges to define what will fulfil it. The team must fulfil or abandon one Product Goal before taking on the next.
| Artifact | Commitment | Example |
|---|---|---|
| Product Backlog | Product Goal | Patients can book, change and pay for appointments online without phoning the clinic |
| Sprint Backlog | Sprint Goal | A patient can book an initial appointment online and receive a confirmation |
| Increment | Definition of Done | Code reviewed, tested on mobile and desktop, accessible and deployed to production |
How to write a useful Product Goal
- Start from the product vision or strategy and the problem you most need to solve next.
- Describe an outcome for users or the business, not a list of features.
- Make it reachable within months rather than years, so the team can see progress.
- Make it testable: you should be able to tell when it has been met.
- Show it above the backlog and review it at every Sprint Review.
For example, "Improve reporting" is a weak Product Goal; "Finance managers can produce the month-end report without exporting to spreadsheets" is a strong one.
Who owns the product backlog?
The Product Owner is accountable for effective product backlog management. Under the 2020 Scrum Guide this includes:
- Developing and explicitly communicating the Product Goal.
- Creating and clearly communicating product backlog items.
- Ordering product backlog items.
- Ensuring that the product backlog is transparent, visible and understood.
The Product Owner may do this work or delegate it to others, but remains accountable. The Product Owner is one person, not a committee.
| Who | What they do with the product backlog |
|---|---|
| Product Owner | Owns the Product Goal, decides the order, makes sure items are understood |
| Developers | Size items, raise technical work and risks, help split and clarify items during refinement |
| Scrum Master | Helps the Product Owner find techniques for Product Goal definition and backlog management |
| Stakeholders and users | Suggest items, give feedback at the Sprint Review, and try to convince the Product Owner when they want the order to change |
In many teams anyone can add an item to the backlog. That is fine, as long as the Product Owner decides where it goes and whether it stays.
What goes into a product backlog?
Types of product backlog items
Product backlog items (PBIs) can describe any work that improves the product. Keeping it all in one list makes honest ordering possible.
| Item type | What it is | Example |
|---|---|---|
| Feature or user story | New capability or change that users will notice | As a patient, I want to reschedule my appointment online so that I do not have to phone |
| Bug | A defect in something already released | Opening hours show the wrong day on mobile |
| Technical debt | Work that keeps the product maintainable and safe to change | Upgrade the logging framework before support ends |
| Spike or research | Time-boxed investigation to reduce uncertainty | Spike: can the diary system accept bookings via its API? |
| Experiment | A small change to test an assumption with real users | Show prices on the booking page to half of visitors and compare completed bookings |
| Non-functional or compliance work | Quality attributes such as accessibility, security or performance | Fix the issues found in the accessibility audit |
| Epic (coarse item) | A large item that will be split later | Insurance claims handled online |
Many teams write features as user stories and group them under epics. Technical work deserves its own place in the order; our guide to technical debt in Scrum explains why.
Product backlog item attributes
The Scrum Guide says attributes vary with the domain of work. Most teams record something like this:
| Attribute | Purpose |
|---|---|
| Description | What is needed and why, often as a user story |
| Order | Its position relative to other items (Product Owner) |
| Size | Relative effort, for example in story points (Developers) |
| Value | The expected benefit or the outcome it supports |
| Acceptance criteria | Conditions that show the item does what it should |
| Type, links and status | Feature, bug, spike or debt; related epic or designs; progress |
How detail changes from top to bottom
A healthy backlog looks like an iceberg: small and detailed at the top, larger and vaguer further down. Detail added months early is often wasted.
| Part of the backlog | Typical horizon | Level of detail |
|---|---|---|
| Top | Next one to two Sprints | Small items, sized, with acceptance criteria; can be Done within one Sprint |
| Middle | The following few Sprints | Medium items or small epics, roughly sized, some open questions |
| Bottom | Later | Large epics and ideas, a single line each, not yet sized |
The DEEP product backlog
A popular checklist for backlog quality is DEEP, an acronym usually credited to Roman Pichler and Mike Cohn. It is not part of the Scrum Guide, but it fits it well.
| Letter | Meaning | Quick check |
|---|---|---|
| D | Detailed appropriately | Can the team explain the top five items without guessing? |
| E | Estimated | Are the next two Sprints' items sized by the Developers? |
| E | Emergent | Did anything change at the last Sprint Review? |
| P | Prioritised (ordered) | If two items tie, does the Product Owner know which goes first? |
If a check fails, fix it at the next refinement session.
How to create a product backlog, step by step
Use this process for a new product, or to rebuild a backlog that has become unmanageable.
- Agree the Product Goal. Write one sentence describing the outcome the team will work towards next. Everything else hangs from it.
- Collect what you already know. Gather requests, ideas, known bugs, technical work and stakeholder commitments, without worrying about detail yet.
- Remove duplicates and unrelated items, noting who asked for each one.
- Group items into epics or themes to show the shape of the work and reveal gaps.
- Write the top items properly. For the items most likely to come first, add a clear description, the reason it matters and draft acceptance criteria. A user story template helps keep them consistent.
- Ask the Developers to size them. Use relative estimates such as story points or T-shirt sizes; see Agile estimation. Split anything too large to finish within one Sprint.
- Order the backlog. Weigh value, risk, dependencies, cost of delay and what you need to learn. Use a technique from the section below if it helps the conversation.
- Check readiness and plan the first Sprint. Make sure roughly one to two Sprints' worth of items at the top are clear and sized, then hold Sprint Planning.
After that first pass, the backlog is maintained through ongoing refinement, Sprint Reviews and regular pruning. Our free product backlog template gives you a ready-made sheet for steps 2 to 8.
Worked example: building a backlog from scratch
A physiotherapy clinic wants patients to stop phoning reception to book. The Product Owner sets the Product Goal: "Patients can book, change and pay for appointments online without phoning the clinic."
Steps 1 and 2: collect, group and filter. A workshop with reception staff, physiotherapists and the IT supplier produces 18 raw ideas. The Product Owner groups them into epics (booking, managing bookings, payments, reminders, staff tools) and moves exercise videos and insurance claims to the bottom, because they do not serve the current Product Goal.
Step 3: write, size and order. After a refinement session with the Developers, the top of the backlog looks like this:
| Order | Item | Type | Size (points) | Why it is here |
|---|---|---|---|---|
| 1 | Spike: confirm the diary system can accept bookings via its API | Spike | 2 | Online booking depends on it; reduces the biggest risk first |
| 2 | Book an initial appointment online (choose clinician, date and time) | Story | 8 | Core to the Product Goal; nothing else works without it |
| 3 | Fix opening hours shown on the wrong day on mobile | Bug | 1 | Tiny, visible to every patient, and confuses bookings |
| 4 | Email confirmation after booking | Story | 3 | High value, small, reassures patients |
| 5 | Cancel a booking online | Story | 3 | Directly reduces phone calls |
| 6 | Reschedule a booking online | Story | 5 | Directly reduces phone calls |
| 7 | SMS reminder 24 hours before the appointment | Story | 5 | Clinic reports no-shows as a cost |
| 8 | Pay a deposit by card when booking | Story | 8 | Part of the Product Goal; needs a payment provider decision |
| 9 | Fix issues from the accessibility audit | Non-functional | 3 | Clinic has committed to fix these this quarter |
| 10 | Staff view of today's online bookings | Story | 5 | Useful for reception, less urgent while volumes are low |
| Later | Insurance claims online | Epic | Not sized | Next Product Goal, not this one |
| Later | Exercise video library | Epic | Not sized | Possible future goal; may be deleted |
Step 4: forecast the first Sprint. The team is new, so it has no velocity yet. In Sprint Planning the Developers look at the top items and judge that items 1 to 4 (14 points) are achievable. The Sprint Goal becomes "A patient can book an initial appointment online and receive a confirmation."
Step 5: adapt. Over the next three Sprints the team completes 13, 16 and 14 points, an average of about 14. Items 5 to 10 total 29 points, so the Product Owner forecasts two to three more Sprints for the remaining Product Goal work and updates that forecast after each Sprint Review.
How to order and prioritise a product backlog
The Scrum Guide uses the word ordered, not prioritised. In practice that means every item has a unique position in one sequence. Labels such as high, medium and low still leave you to decide which high item goes first; an ordered list makes that decision explicit.
Order is not only about value. The Product Owner weighs several factors:
| Factor | Question to ask |
|---|---|
| Value | How much does this help users or the business reach the Product Goal? |
| Cost of delay | What do we lose for each Sprint we wait? Is there a deadline? |
| Risk | Would doing this early reveal a problem we cannot afford to find late? |
| Dependencies | Does something else need this first? |
| Size | How much effort does it take? Small, valuable items are cheap wins. |
| Learning | Will this give us feedback that changes what we do next? |
Prioritisation techniques compared
Techniques give structure to the conversation. None of them replaces the Product Owner's judgement, and none is required by Scrum.
| Technique | How it works | Best for | Watch out for |
|---|---|---|---|
| MoSCoW | Sort items into Must have, Should have, Could have and Won't have (this time); originated in DSDM | Agreeing scope for a release or Product Goal with stakeholders | Too many Musts; it groups items rather than ordering them |
| Value vs effort | Plot items on a two-by-two grid of value against size | Quick visual sorting in a workshop | Ignores risk and dependencies |
| WSJF (weighted shortest job first) | Cost of delay divided by job size; widely used in SAFe and based on Don Reinertsen's work | Large backlogs where timing matters | Scores can look precise when they are guesses |
| RICE | (Reach x Impact x Confidence) / Effort; popularised by Intercom | Product teams with usage data | Needs reasonable reach estimates |
| Kano model | Classifies features as basic expectations, performance features or delighters | Understanding what users really expect | Needs user research to be reliable |
Worked example: scoring and ordering six items
The clinic's Product Owner uses a simple WSJF-style score for six middle-of-the-backlog items. Value, time criticality and risk reduction are each scored from 1 to 10 in a short session with stakeholders; size comes from the Developers. Score = (value + time criticality + risk reduction) / size.
| Item | Value | Time criticality | Risk reduction | Size | Score |
|---|---|---|---|---|---|
| Spike: choose a payment provider | 1 | 3 | 8 | 2 | 6.0 |
| Fix accessibility audit issues | 5 | 8 | 3 | 3 | 5.3 |
| Reschedule a booking online | 8 | 5 | 1 | 5 | 2.8 |
| SMS reminder 24 hours before | 7 | 6 | 1 | 5 | 2.8 |
| Staff view of today's bookings | 6 | 2 | 1 | 5 | 1.8 |
| Pay a deposit by card | 6 | 3 | 2 | 8 | 1.4 |
The scores suggest an order; the Product Owner decides. Here rescheduling goes above reminders because reception gets more calls about changes than about forgotten appointments. Card deposits stay low until the payment spike reports back.
Refining the product backlog
Product backlog refinement is the ongoing activity of breaking down and adding detail to items, such as a description, order and size. It is not one of the five Scrum events; teams fit it in wherever it works, often as one or two short sessions per Sprint plus informal conversations. The 2020 Scrum Guide sets no time limit, so inspect and adapt the amount you spend.
A typical session:
- The Product Owner brings the next few items and explains the need and the context.
- The Developers ask questions, raise risks and suggest simpler options.
- Together they draft or improve acceptance criteria.
- Items that are too large are split into thin slices that still deliver value.
- The Developers size the items.
- The Product Owner adjusts the order if anything new was learned.
Splitting example. "Pay a deposit by card when booking" (8 points) is split into "Pay a deposit by debit or credit card" (5), "Receive a deposit receipt by email" (2) and "Refund the deposit when cancelling more than 24 hours ahead" (3). The parts add up to more than the original estimate, which is common: splitting often reveals work nobody had noticed.
For techniques, agendas and timings, see our full guide to backlog refinement.
Definition of Ready: optional, not Scrum
Some teams agree a Definition of Ready, a checklist an item must meet before it can enter Sprint Planning. The Scrum Guide does not include one; it only says items that can be Done within one Sprint are ready for selection. A light checklist (clear description, drafted acceptance criteria, sized, fits in one Sprint, dependencies visible) can help. Keep it short: a long one becomes a stage gate that delays learning.
From product backlog to Sprint Planning
Items leave the product backlog when they are selected in Sprint Planning. The Scrum Team agrees a Sprint Goal, and the Developers select the items they forecast they can complete. Those items, the Sprint Goal and the Developers' plan form the Sprint Backlog.
Use recent velocity as a guide to how much to select, adjusted for holidays and other capacity changes. If an item is not Done at the end of the Sprint, it returns to the product backlog for the Product Owner to reorder.
The Sprint Review closes the loop: the team shows what was done, stakeholders give feedback, and the product backlog is adjusted to meet new opportunities. A sprint planning template helps you record capacity, the Sprint Goal and the selected items.
Product backlog vs sprint backlog
| Product backlog | Sprint backlog | |
|---|---|---|
| Contents | Everything that might improve the product | The Sprint Goal, the selected items and the plan for delivering them |
| Accountable | Product Owner | Developers |
| Commitment | Product Goal | Sprint Goal |
| Time horizon | The life of the product | One Sprint |
| How it changes | Continuously, as the Product Owner reorders, adds and removes items | Updated by the Developers throughout the Sprint as they learn |
Keeping the product backlog healthy
Backlogs tend to grow faster than teams can deliver. These checks, which are our own suggestions rather than Scrum rules, help you spot problems early.
| Check | Healthy sign | Warning sign |
|---|---|---|
| Ready items | About one to two Sprints' worth of refined, sized items at the top | Sprint Planning keeps stalling on unclear items |
| Size of the list | The Product Owner can explain why each item is there | Hundreds of items nobody has read in months |
| Age | Few items older than a year | Many items untouched since they were created |
| Link to the Product Goal | Top items clearly serve the current goal | The top is full of unrelated requests |
| Mix of work | Features, bugs and technical work all appear in the order | Technical debt never rises near the top |
How to prune an overgrown backlog
- Export or list every item with its creation date and last update.
- Delete duplicates and items that no longer fit the product.
- Archive items older than an agreed age (for example 12 months) that nobody has championed; good ideas tend to come back.
- Re-order what remains against the current Product Goal.
- Tell stakeholders what was removed and how to raise it again if it matters.
Clear ordering against a Product Goal is one of the best defences against scope creep.
Common product backlog mistakes
| Mistake | Why it hurts | What to do instead |
|---|---|---|
| A backlog that only grows | The important items are buried and refinement takes longer each Sprint | Prune regularly and delete items that no longer serve the Product Goal |
| Several backlogs for one product | Teams optimise locally and nobody can order work across the product | One product backlog and one Product Owner, with views or filters per team |
| Everything is high priority | Labels hide the real decisions | Keep one strict order |
| Too much detail too early | Specifications for distant items are rewritten or thrown away | Detail the top; keep the rest coarse |
| The Product Owner works alone | Items are unclear and sizes are guesses | Refine with the Developers and involve stakeholders |
| No Product Goal | The backlog becomes a list of requests rather than a plan for value | Agree and display a Product Goal |
| Technical work kept off the backlog | Debt accumulates invisibly and slows every Sprint | Make technical items visible and order them alongside features |
Product backlog templates and tools
You do not need special software to start. A spreadsheet or a wall of sticky notes works for a single team. Our free product backlog template for Google Sheets, Excel and PDF has columns for Order, ID, Item / user story, Type, Value (1-10), Estimate (points), Ready?, Sprint and Status, with dropdowns for item type and readiness.
Move to a tool when several teams share the backlog or stakeholders need a live view. Jira is the most common choice for software teams and has a dedicated backlog view. Wrike, our top-rated tool overall, suits teams that need the backlog to sit alongside wider portfolio, resource and reporting needs.
Free templates for this topic
Frequently asked questions
What is a product backlog in Scrum?
It is an emergent, ordered list of what is needed to improve the product, and the single source of work for the Scrum Team. Its commitment is the Product Goal, and the Product Owner is accountable for it.
Who owns the product backlog?
The Product Owner is accountable for it, including the Product Goal, the items and their order. Others can help, but the accountability stays with the Product Owner.
Who can add items to the product backlog?
Anyone can suggest items, and in many teams Developers and stakeholders add them directly. The Product Owner decides whether an item stays and where it goes in the order.
What is the difference between a product backlog and a sprint backlog?
The product backlog covers everything that might improve the product for its whole life and belongs to the Product Owner. The sprint backlog is the Sprint Goal, the items selected for one Sprint and the Developers' plan, and belongs to the Developers.
Why does Scrum say ordered rather than prioritised?
Priority labels such as high, medium and low leave ties. Ordering puts every item in one sequence that can reflect value, risk, dependencies and learning.
How big should a product backlog be?
There is no rule. A useful test is whether the Product Owner can explain why each item is there. Keep detailed items to a few Sprints' worth and hold the rest as coarse epics.
How often should the product backlog be refined?
Continuously. Most teams hold one or two short refinement sessions per Sprint. The 2020 Scrum Guide sets no time limit; the old guidance of no more than 10% of capacity was removed.
Do product backlog items have to be user stories?
No. The Scrum Guide does not prescribe a format. User stories are popular for features, but bugs, technical tasks and spikes are often clearer as plain descriptions.
Who estimates product backlog items?
The Developers who will do the work are responsible for sizing. The Product Owner helps them understand items and trade-offs but should not set the estimates.
When is a product backlog item ready?
The Scrum Guide says items that can be Done within one Sprint are deemed ready for selection in Sprint Planning. Some teams add a short Definition of Ready, which is optional.
Can multiple teams share one product backlog?
Yes. Teams working on the same product share one Product Goal, product backlog and Product Owner.
Is the product backlog the same as a product roadmap?
No. A roadmap shows direction and themes over quarters or years. The product backlog lists the specific work needed next, in order, and changes far more often.
Do bugs and technical debt belong in the product backlog?
Yes. Putting them in the same list as features lets the Product Owner order all work honestly, and stops important maintenance from being forgotten.