Kanban guide · Kanban compared
Kanban vs Agile: Differences, Overlap and When to Use Each
Kanban vs Agile is not a choice between two rival methods: Agile is a set of values and principles for delivering work in small increments and adapting to change, while Kanban is a flow-based method that many teams use to work in an Agile way. The real decision is between Kanban's continuous flow and time-boxed Agile frameworks such as Scrum. This guide explains how the two relate, compares boards, planning and metrics, works through a real-world style example and gives you a step-by-step process for choosing.
Key takeaways
- Agile is a philosophy set out in the 2001 Agile Manifesto; Kanban is a method for managing and improving the flow of work. They sit at different levels, so they are not alternatives.
- Kanban comes from Lean and the Toyota Production System, not from the Agile software movement, but it fits the Manifesto's values closely and is widely counted as an Agile approach.
- There are two main definitions of Kanban today: the Kanban Method (Kanban University) and The Kanban Guide (Vacanti and Coleman, edition 2025.5). Both centre on visualising work, limiting work in progress and improving flow.
- The practical comparison is flow vs time-box: Kanban has no sprints or prescribed roles and measures cycle time and throughput, while Scrum uses fixed Sprints, three accountabilities and Sprint Goals.
- Kanban suits work that arrives unpredictably or continuously; time-boxed frameworks suit a dedicated team building a product towards planned goals. Many teams combine the two.
Kanban vs Agile: the short answer
Agile is a mindset for delivering value in small, frequent increments, collaborating closely with customers and adapting the plan as you learn. Kanban is a method for visualising work, limiting how much is in progress and improving the flow of items from request to delivery. Agile tells you what to value; Kanban gives you one practical way to act on those values.
| Agile | Kanban | |
|---|---|---|
| What it is | A set of values and principles | A method for managing and improving flow |
| Defined by | The Agile Manifesto (2001): 4 values, 12 principles | The Kanban Method (Kanban University) and The Kanban Guide (edition 2025.5) |
| Roots | Lightweight software development methods of the 1990s | Lean thinking and the Toyota Production System |
| Tells you | What to value and why | How to see, limit and improve the work in your system |
| Relationship | The umbrella | One of the approaches used under it |
So the real question is not Agile or Kanban, but continuous flow, fixed Sprints, or a mix.
What is Agile?
Agile is an approach to product and project work that delivers in short cycles, uses feedback to steer and treats the plan as something to update rather than defend. It was named in February 2001, when 17 software practitioners wrote the Agile Manifesto. The Manifesto values individuals and interactions over processes and tools, working software over comprehensive documentation, customer collaboration over contract negotiation, and responding to change over following a plan.
Twelve principles add detail. Among them: satisfy the customer through early and continuous delivery; welcome changing requirements, even late in development; deliver working software frequently, preferring shorter timescales; maintain a sustainable pace indefinitely; and, at regular intervals, reflect on how to become more effective and adjust.
Just as important is what Agile does not contain. It prescribes no roles, meetings, iteration length, board or metric. Those come from the frameworks and methods that put Agile into practice, including Scrum, Kanban, Extreme Programming (XP), Lean software development, Scrumban and scaled frameworks such as SAFe.
What is Kanban?
"Kanban" is Japanese for signboard or visual signal. At Toyota, from the late 1940s onwards, cards travelled with parts and signalled when an upstream process should make more, so that production followed real consumption rather than a forecast. That is the origin of the pull system, explained in our guide to pull vs push systems.
Applied to knowledge work, Kanban grew from David J. Anderson's work with software teams, starting with a project at Microsoft in 2004 and continuing at Corbis, and was described in his 2010 book *Kanban: Successful Evolutionary Change for Your Technology Business*. Today two well-known sources define it.
The Kanban Method (Kanban University)
Kanban University's official guide describes Kanban as a method for defining, managing and improving services that deliver knowledge work. It sets out three change management principles (start with what you do now; agree to pursue improvement through evolutionary change; encourage acts of leadership at all levels), three service delivery principles (understand and focus on customer needs and expectations; manage the work and let people self-organise around it; regularly review the network of services and its policies) and six general practices:
- Visualise the work and the workflow.
- Limit work in progress (WIP).
- Manage flow.
- Make policies explicit.
- Implement feedback loops, such as a daily team Kanban meeting and regular replenishment and retrospectives.
- Improve collaboratively, evolve experimentally.
The Kanban Guide (Vacanti and Coleman)
The Kanban Guide, written by Daniel Vacanti and John Coleman (current edition 2025.5, May 2025), defines Kanban as a strategy for optimising the flow of value through a process. It has three practices: defining and visualising a workflow, actively managing items in a workflow, and improving a workflow. It requires four flow measures: WIP (items started but not finished), throughput (items finished per unit of time), work item age (time since an unfinished item started) and cycle time (time from start to finish).
The two differ in emphasis but agree on the core: make work visible, limit WIP so that work is pulled rather than pushed, and use data to improve. Neither prescribes roles, Sprints or estimation. For the principles in more detail, see Kanban principles and practices, or start with what is Kanban.
Is Kanban Agile?
In practice, yes: Kanban is almost always listed among Agile approaches, and most Agile teams use a Kanban board at some level. The nuance is that Kanban was not created from the Agile Manifesto. Its roots are Lean manufacturing, and The Kanban Guide does not mention Agile at all; it draws on Lean principles, systems thinking and the Toyota Production System. The Kanban Method describes itself as a way to manage any professional service, Agile or not.
It is accurate to say Kanban is a Lean method that is fully compatible with, and widely used for, Agile ways of working.
| Lean | Agile | Kanban | |
|---|---|---|---|
| Origin | Toyota Production System; named "Lean" in the late 1980s | Agile Manifesto, 2001 | Toyota kanban cards; adapted for knowledge work in the 2000s |
| Core idea | Maximise customer value, remove waste, create flow | Deliver small increments, collaborate, adapt to change | Visualise work, limit WIP, manage and improve flow |
| Unit of improvement | The whole value stream | The team and its product | The workflow (service) the team runs |
How Kanban puts the 12 Agile principles into practice
A useful way to judge whether a method is Agile is to check it against the twelve principles. The table below is our own mapping, not part of either official document. The third column shows where Kanban says little and you need to add a practice of your own.
| Agile principle (summarised) | How Kanban supports it | What you may need to add |
|---|---|---|
| 1. Early and continuous delivery of value | Items flow to Done one at a time; nothing waits for the end of a cycle | A clear Definition of Done so "done" means usable |
| 2. Welcome changing requirements | Anything not yet past the commitment point can be reordered at the next replenishment | A product owner or service manager who decides order |
| 3. Deliver frequently, shorter timescales preferred | Cycle time is measured and reduced; small items are encouraged | Technical ability to release often (see continuous delivery) |
| 4. Business and developers work together daily | Daily Kanban meeting at the board; stakeholders can see the board | An explicit invitation for stakeholders to attend reviews |
| 5. Build projects around motivated individuals | "Manage the work, let people self-organise around it" | Little beyond this; it is close to the Manifesto |
| 6. Face-to-face conversation | Not addressed directly | Team norms for conversation, especially for remote teams |
| 7. Working software is the measure of progress | Throughput counts finished items, not effort | Avoid counting partly done work as progress |
| 8. Sustainable pace | WIP limits stop overload and constant task switching | Respect the limits under pressure |
| 9. Technical excellence and good design | Not addressed directly | Engineering practices such as testing and refactoring (XP) |
| 10. Simplicity: maximise work not done | Explicit policies and a visible backlog make low-value work easy to drop | Regular backlog pruning |
| 11. Self-organising teams | People pull work; no one assigns tasks to full queues | Agreement on how the team handles expedites |
| 12. Regular reflection and adjustment | Feedback loops and "evolve experimentally" | A fixed retrospective cadence so improvement is not skipped |
Kanban vs time-boxed Agile frameworks: key differences
Because Agile itself prescribes no practices, the meaningful comparison is between Kanban and the time-boxed frameworks people usually mean by "Agile", most often Scrum. The Scrum column below follows the 2020 Scrum Guide.
| Aspect | Kanban | Time-boxed Agile (e.g. Scrum) |
|---|---|---|
| Cadence | Continuous flow; meetings on a cadence the team chooses | Fixed-length Sprints of one month or less, back to back |
| Planning | Replenishment as often as needed; just-in-time | Sprint Planning at the start of each Sprint |
| Commitment | Per item, at the commitment point | To a Sprint Goal for the whole Sprint |
| Roles | None prescribed; keep your current roles | Product Owner, Scrum Master, Developers |
| Change during a cycle | New items can enter whenever capacity frees up | Scope can be renegotiated, but changes that endanger the Sprint Goal are avoided |
| Limiting work | Explicit WIP limits per column or per system | Indirectly, by what fits in the Sprint |
| Estimation | Optional; many teams use item counts and right-sizing | Common (story points), though not required by the Scrum Guide |
| Core metrics | WIP, throughput, cycle time, work item age | Velocity, Sprint burndown, Sprint Goal success |
| Board | Persistent; reflects the real workflow | Often reset each Sprint |
| Release | Whenever an item is done | At least one usable Increment per Sprint; can release more often |
| Starting point | Your current process, changed gradually | Adopt the framework's roles and events |
| Best-fit work | Unpredictable arrivals, support, operations, mixed requests | New product or feature development by a dedicated team |
For a full side-by-side, including ceremonies and boards, read Kanban vs Scrum.
Agile (Scrum) board vs Kanban board
Both boards show cards moving left to right, which is why they are often confused. The difference is in the rules, not the columns.
- Lifespan: a Scrum board usually holds the current Sprint Backlog and is cleared at the end of each Sprint. A Kanban board is persistent: items stay until they are done, however long that takes.
- WIP limits: a Kanban board shows a limit on columns or on the whole system. A Scrum board normally has none, because the Sprint itself caps the work.
- Commitment point: a Kanban board marks the point where an option becomes a commitment (often between "Options" and "Ready"). On a Scrum board the commitment happens at Sprint Planning.
- Explicit policies: Kanban boards often show entry and exit criteria for each column, such as "Ready = acceptance criteria agreed".
- Classes of service: Kanban teams may add an expedite lane or colour code for fixed-date items. See Kanban swimlanes.
Example layout
| Options | Ready (limit 4) | In progress (limit 3) | Review (limit 2) | Done |
|---|---|---|---|---|
| Ideas and requests not yet committed | Agreed and prioritised; pulled from here | Being worked on | Waiting for check or sign-off | Delivered to the customer |
Learn more in our guides to Kanban boards and Scrum boards, or set one up quickly with the free Kanban board template.
Agile metrics vs Kanban metrics
Time-boxed teams tend to measure how much they finish per Sprint; Kanban teams measure how long items take and how many finish per week. Both are useful, and many teams track both.
| Metric | Typical in | What it tells you | Watch out for |
|---|---|---|---|
| Velocity | Scrum | Story points completed per Sprint, used for forecasting | Not comparable between teams; easy to inflate |
| Sprint burndown | Scrum | Work remaining in the Sprint | Says nothing about flow after the Sprint |
| WIP | Kanban | How many items are started but not finished | Count items, not people |
| Throughput | Kanban | Items finished per week | Needs items of broadly similar size |
| Cycle time | Kanban | Time from start to finish for each item | Use percentiles, not only the average |
| Work item age | Kanban | How long unfinished items have been in progress | Old items are your early warning |
Worked example: Little's Law
Little's Law, first proved by John Little in 1961, links three of the Kanban measures: average cycle time = average WIP / average throughput. Suppose your team usually has 12 items in progress and finishes 4 a week. On average an item takes 12 / 4 = 3 weeks from start to finish. If you cap WIP at 6 and throughput stays at 4 a week, average cycle time falls to 6 / 4 = 1.5 weeks. Nobody worked faster; items simply spent less time waiting.
The law holds over the long run only when the system is stable (roughly as many items start as finish, and items are not abandoned), so use it to understand your system rather than to promise dates. Compare with the Agile velocity chart and cycle time.
Worked example: one team, two Agile ways
The following example is illustrative: the team and figures are invented to show the mechanics, not taken from a study.
A five-person internal digital team at a regional housing association looks after the tenant website and portal. Its work is a mix: about 60% planned improvements (a new repairs-booking journey, accessibility fixes) and about 40% unplanned requests (content changes, urgent bugs, requests from the call centre).
Version A: two-week Sprints
- Sprint Planning every other Monday picks enough planned work to fill about 80% of capacity, leaving a buffer for urgent requests.
- Urgent bugs interrupt the Sprint two or three times a week. The team often misses its Sprint Goal and the buffer is either too big or too small.
- Content requests from the call centre wait up to two weeks for the next Sprint unless someone treats them as urgent.
- The repairs-booking journey gets focused attention, and the Sprint Review gives tenants' representatives a regular slot to see progress.
Version B: Kanban
- Board columns: Options, Ready (limit 5), Build (limit 3), Test (limit 2), Done.
- Two classes of service: Expedite (one item at a time, may exceed limits) for portal outages, and Standard for everything else.
- Cadences: 15-minute daily meeting at the board; weekly replenishment with the service manager to choose what moves into Ready; monthly service delivery review with call-centre and housing leads; monthly retrospective.
- Planned and unplanned work share one board, so the trade-off between them is visible and decided at replenishment rather than in the middle of a Sprint.
What six weeks of data showed
| Measure | Sprints (weeks 1 to 6) | Kanban (weeks 7 to 12) |
|---|---|---|
| Average WIP | 11 items | 6 items |
| Throughput | 5 items a week | 5.5 items a week |
| Average cycle time | about 2.2 weeks | about 1.1 weeks |
| Content requests: typical wait | up to 2 weeks | 2 to 4 days |
| Repairs-booking journey | steady progress, visible each Sprint | progress slowed in week 8 until the team reserved 2 of the 3 Build slots for planned work |
The lesson is not that Kanban "won". Kanban suited this team's mixed, interrupt-driven work, but it needed an explicit policy (reserving Build capacity) to protect the planned project, something Sprints had provided for free. A team whose work was almost all planned product development would probably have kept Sprints. Plan replenishment and reviews using our guide to Kanban ceremonies.
When to use Kanban (and when a time-boxed framework fits better)
| Situation | Usually a good fit | Why |
|---|---|---|
| IT support, service desk or operations | Kanban | Work arrives continuously and urgently; flow handles it without breaking a Sprint |
| A dedicated team building a new product | Scrum or another time-boxed framework | Sprint Goals and regular reviews give focus and a predictable feedback rhythm |
| Marketing, HR or finance teams new to Agile | Kanban | Starts from the current process; no new roles to introduce |
| A Scrum team constantly interrupted by urgent work | Scrumban or Kanban | Keeps some structure but adds WIP limits and flow |
| Maintenance of a mature product with frequent small releases | Kanban | Items are small and independent; continuous delivery fits |
| Many teams working on one large solution | A scaled framework, often with Kanban at portfolio level | Needs shared planning across teams; SAFe, for example, uses a Portfolio Kanban |
None of these is a rule, which is why the next section gives you a process rather than a verdict.
How to choose: a step-by-step decision process
- Describe your work. Mark the last 30 items your team finished as planned or unplanned, and note how urgent each was on arrival.
- Check how predictable arrivals are. If more than about a third were unplanned and needed doing within days, Sprints will be interrupted often.
- Check whether you need a shared goal per cycle. One product heading for a release benefits from a Sprint Goal; a team serving many requesters often does not.
- Look at your stakeholders. Do they want regular review dates or quick turnaround on individual requests?
- Consider how much change you can absorb. Scrum adds new accountabilities and events; Kanban starts with what you do now.
- Score the options below, choose, and agree a date (say, eight weeks out) to review the data and adjust.
Decision scorecard
Score each statement from 1 (disagree) to 5 (agree). A higher left-hand total points to Kanban, a higher right-hand total to a time-boxed framework; close scores suggest Scrumban.
| Points towards Kanban | Score | Points towards time-boxed Agile | Score |
|---|---|---|---|
| Work arrives unpredictably | 1 to 5 | Work is mostly planned weeks ahead | 1 to 5 |
| Items are small and independent | 1 to 5 | Items combine into a larger product increment | 1 to 5 |
| We serve many requesters | 1 to 5 | We serve one product and one product owner | 1 to 5 |
| We want to change our process gradually | 1 to 5 | We are ready to adopt new roles and events | 1 to 5 |
| Fast turnaround matters more than a fixed cadence | 1 to 5 | A fixed rhythm of review and planning matters most | 1 to 5 |
If you choose time-boxing, our what is a Sprint guide and free Sprint planning template will help you start.
How to introduce Kanban in an Agile team
- Map your current workflow. Write down the real stages work goes through today, including waiting stages such as "awaiting approval".
- Build the board. One column per stage, plus Options and Done. Put every item currently in progress on it, including the ones nobody likes to admit to.
- Agree the commitment point and Definition of Done. Decide where an idea becomes a commitment and what "done" means for your customers.
- Set initial WIP limits. A common starting point is around the number of people working in a stage, or slightly lower. Treat the first limits as an experiment.
- Make policies explicit. Write entry and exit criteria for columns, how to handle expedites, and how blocked items are shown.
- Start the cadences. A short daily meeting at the board, a replenishment meeting, and a regular review and retrospective.
- Measure from day one. Record start and finish dates for every item so that WIP, throughput, cycle time and work item age are available after a few weeks.
- Improve one thing at a time. Use the data to find the biggest queue or most frequent blocker, change one policy, and check the effect.
Track ageing items with a WIP aging chart.
Combining Kanban with other Agile frameworks
Kanban is designed to be applied to an existing process, so it combines readily with other approaches.
- Scrum with Kanban practices: a Scrum team keeps its Sprints, roles and events but adds WIP limits, flow metrics and explicit policies to the Sprint Backlog. This is permitted by the Scrum Guide, which leaves the team free to choose its own practices.
- Scrumban: a hybrid that started as a way to move from Scrum to Kanban (described by Corey Ladas in 2008) and is now often used as a lasting mix of planning cadence and flow. See Kanban vs Scrumban.
- Scaled frameworks: SAFe uses Kanban systems to manage the flow of epics at portfolio level, alongside time-boxed iterations for teams. See SAFe.
For the full family of approaches, read types of Agile methodologies, and for the Scrum side specifically, Agile vs Scrum.
Common misconceptions and mistakes
- "We have a board, so we do Kanban." A board without WIP limits, explicit policies and flow measurement is a visual to-do list. Useful, but not Kanban.
- "Kanban means no planning." Kanban plans continuously through replenishment and uses throughput data to forecast. It simply does not tie planning to a fixed time-box.
- "Kanban means no deadlines." Fixed-date work is handled as a class of service and prioritised so that it finishes in time.
- Setting WIP limits and then ignoring them. If the limit is always exceeded, either change it deliberately or treat the breach as a signal to swarm on blocked work.
- Measuring people instead of flow. Cycle time and throughput describe the system. Using them to rank individuals encourages gaming and hides problems.
- Dropping reflection. Without Sprints forcing a retrospective, some Kanban teams stop improving. Put a retrospective in the calendar.
Advantages and limitations of Kanban as an Agile approach
| Advantages | Limitations |
|---|---|
| Starts from your current process, so it is easy to adopt | Gives little guidance on roles; unclear ownership of priorities can cause problems |
| Handles unpredictable and urgent work without breaking a cycle | Without a Sprint Goal, a team can lose focus on a larger objective |
| WIP limits reduce overload and shorten cycle time | Requires discipline to respect limits under pressure |
| Flow metrics give realistic forecasts based on real data | Forecasts need several weeks of data before they are reliable |
| Works for any type of knowledge work, not only software | Silent on engineering quality; software teams need to add practices |
If you are weighing Kanban against a traditional plan-driven approach instead, read Kanban vs Waterfall.
Frequently asked questions
Is Kanban Agile?
Yes, in practice. Kanban is usually listed among Agile approaches because it delivers value continuously, welcomes changing priorities and builds in regular reflection. Strictly, it comes from Lean manufacturing rather than the Agile Manifesto, so it is best described as a Lean method that fits Agile values.
What is the difference between Kanban, Agile and Scrum?
Agile is the philosophy: four values and twelve principles. Scrum and Kanban are two ways to apply it. Scrum uses fixed-length Sprints, three accountabilities and five events; Kanban uses continuous flow, WIP limits and flow metrics, without prescribed roles or Sprints.
Does Kanban have sprints?
No. Kanban uses continuous flow: items are pulled when there is capacity and released when they are done. Teams still hold regular meetings, such as replenishment and reviews, but they are not tied to a delivery time-box. If you want Sprints with Kanban practices, look at Scrumban.
Which is better, Agile or Kanban?
Neither, because they are not alternatives. Kanban is one way of being Agile. The useful question is whether continuous flow (Kanban) or fixed time-boxes (such as Scrum) suit your work better; the decision process above helps you answer it.
Is Kanban Agile or Lean?
Both. Kanban's origins are in the Toyota Production System and Lean thinking, and The Kanban Guide does not mention Agile. Because it shares Agile's focus on customer value, feedback and improvement, it is widely used and taught as an Agile approach too.
Is Kanban a methodology or a framework?
It is usually called a method: the Kanban Method. It provides principles and practices that you apply to your existing process, rather than a complete framework of roles and events. The Kanban Guide calls it a strategy for optimising the flow of value.
Does Kanban have roles?
Neither the Kanban Method nor The Kanban Guide requires roles. Some teams use optional roles such as a service request manager (who orders incoming work) and a service delivery manager (who looks after flow), but you can keep your existing job titles.
Can you use Kanban without Scrum?
Yes. Many teams practise Agile using Kanban alone. Kanban needs a visual workflow, WIP limits, explicit policies and feedback loops, none of which depends on Scrum.
Is a Kanban board in Jira or Trello automatically Agile?
No. A tool's board view is a way of displaying work. It becomes Kanban when you add WIP limits, explicit policies and flow measurement, and it supports Agile when the team uses it to deliver small increments and adapt based on feedback.
Is Kanban iterative?
Kanban is incremental and continuous rather than iterative in fixed cycles. Each item is delivered when finished, and the process is improved through regular feedback loops.
Can non-software teams use Kanban as their Agile approach?
Yes. Marketing, HR, finance, legal, operations and construction teams often use Kanban as their entry point to Agile because it starts with their current process and needs no new roles or Sprints.