Kanban Ceremonies: The 7 Cadences and How to Run Them

Kanban ceremonies are the regular meetings and reviews a Kanban team uses to coordinate work, choose what to start, check delivery against customer expectations and improve its process. Kanban University calls them cadences and describes seven, from a daily Kanban meeting to a quarterly strategy review, but none is mandatory and the Kanban Guide prescribes none. This guide explains what each cadence is for, who attends, how to run it, and how to choose the few your team actually needs.

Key takeaways

  • Kanban has no fixed ceremonies in the Scrum sense. The Kanban Method calls its meetings cadences: feedback loops held at a rhythm that suits the work.
  • Kanban University's 2015 model has seven cadences; its Official Guide also names three team-level ones: a daily Kanban meeting, team replenishment and a team retrospective.
  • The Kanban Guide (2025.5) requires no meetings and says changes need not wait for a regular cadence.
  • The daily Kanban meeting walks the board from right to left and asks what is stopping each item from flowing, not what each person did yesterday.
  • The service delivery review compares delivery with customer expectations, such as the share of items finished within the service level expectation.
  • Start with the meetings you already hold, add a daily meeting and replenishment, and combine cadences on small teams.

What are Kanban ceremonies?

Kanban ceremonies, more accurately called Kanban cadences, are recurring meetings and reviews in which a team or group of services looks at information about its work and acts on it. Kanban University's glossary defines a cadence as a type of meeting or review providing feedback from one or more services, and adds that feedback information without action is not a feedback loop.

Cadences put one of the six general practices of the Kanban Method into effect: implement feedback loops. Without them, a board shows problems but nobody is obliged to look at them at a set time. With them, blocked work is raised daily, delivery is compared with expectations every week or two, and the system itself is redesigned when the evidence says it should be. Our guide to Kanban principles and practices explains how this practice sits alongside visualising work, limiting WIP and making policies explicit.

The word "ceremony" is borrowed from everyday Scrum usage, although the 2020 Scrum Guide itself calls its meetings events; our guide to Agile ceremonies covers those Scrum events. Kanban University uses "cadence" instead, and its material treats the frequency, length and attendees of each one as adjustable. You choose which to hold and how often, based on how quickly your work arrives and how many teams depend on each other.

What each Kanban source requires

Two bodies publish definitions of Kanban for knowledge work, and they treat meetings differently. Knowing which one you are following avoids arguments about whether a team is "doing Kanban properly".

SourceWhat it says about meetingsPractical meaning
David J. Anderson, "Kanban Cadences", Kanban University (2015)Seven cadences; adapt existing meetings rather than adding seven new ones; combine them at small scaleA menu to design from, not a checklist
Kanban University, Official Guide to the Kanban Method (2022)Three team-level cadences (daily Kanban meeting, team retrospective, internal team replenishment) plus service-oriented cadences; reuse and evolve existing meetingsA team can start with three meetings and add service-level reviews later
Coleman and Vacanti, The Kanban Guide (edition 2025.5)No required meetings. Reviewing the Definition of Workflow is common, but there is no need to wait for a formal meeting to change itImprovement can happen just in time, whenever the data shows a problem

The two views are compatible in practice. Most teams following either source hold a short daily meeting and some form of regular replenishment, because those are the cheapest ways to keep work flowing. Where they differ is on the higher-level reviews, which only the Kanban Method describes. This guide uses Kanban University's names, because only the Kanban Method describes the full set.

The seven Kanban cadences at a glance

The table below lists the seven cadences from Anderson's 2015 model. Frequencies and lengths are the "typical configurations" given in a 2015 Lean Kanban Inc. (now Kanban University) presentation by Janice Linden-Reed, Kanban Cadences and Information Flow, which stresses that each should be adjusted to the organisation. Anderson's own article confirms a fortnightly service delivery review and a weekly replenishment meeting for one client.

CadenceTypical frequencyTypical lengthWho attendsQuestion it answers
Kanban meetingDaily10 to 20 minutesThe team doing the workWhat is blocking flow today, and how do we finish it?
Replenishment (commitment) meetingWeekly20 to 30 minutesWhoever sets priorities, plus team representativesWhich options do we commit to start next?
Delivery planning meetingVaries with the delivery cadence1 to 2 hoursTeam, release and operations staff, customer representativesWhat will we hand over, when, and who must be ready?
Service delivery reviewTwice a month30 minutesService owner, team leads, customer representativesAre we meeting customers' expectations, and what should change?
Risk reviewMonthly1 to 2 hoursService owners, managers, people who see the blockersWhat is likely to stop us delivering, and how do we respond?
Operations reviewMonthly2 hoursManagers and representatives of interdependent servicesIs the network of services working as a whole?
Strategy reviewQuarterlyHalf a daySenior leaders and service ownersAre we offering the right services to the right customers?

Read the table from top to bottom as a move from today's work to the organisation's direction. The lower four depend on delivery data, and the last three pay off mainly when more than one team or service is involved. A single team with one customer group rarely needs separate operations and strategy reviews.

Team-level cadences

For a single team, the Official Guide to the Kanban Method from Kanban University suggests three cadences, with these frequencies and purposes:

Team cadenceFrequency in the Official GuidePurpose in the Official Guide
Team Kanban meetingDailyTo observe and track the status and flow of work (not the workers)
Team retrospectiveBiweekly or monthlyReflect on how the team manages its work and how it can improve
Internal team replenishment meetingWeekly or as neededSelect items from the pool of work to do next

These three are the realistic starting set for most teams. The daily meeting keeps work moving, replenishment keeps the right work entering, and the retrospective changes the system. The same guide asks teams to identify existing meetings that already serve a similar purpose and evolve them, which follows the principle of starting with what you do now.

The daily Kanban meeting

The daily Kanban meeting is a short meeting at the board where the team coordinates the flow of work. Its distinguishing feature is that it reviews the work, not the workers: instead of each person reporting in turn, the team walks the board from right to left, starting with items closest to done, and asks what is keeping each one from flowing and who can help.

Walking right to left reflects a simple rule of flow: finishing work releases capacity and delivers value, starting new work does neither. An item one step from Done deserves attention before an item that has just begun.

A 15-minute agenda

  1. Blocked items (2 to 4 minutes). For each blocked card: what is the blocker, who is resolving it, and is an escalation needed today?
  2. Ageing items (3 to 4 minutes). Compare each in-progress item's age with the service level expectation (SLE). Items past a threshold the team chooses, such as 70% of the SLE, get a plan; items past the SLE get help. A WIP aging chart shows this in seconds.
  3. Walk the board right to left (5 to 6 minutes). Column by column, ask what is needed to move each item on. Skip cards that are moving normally.
  4. WIP check (1 minute). Is any column over its WIP limit? If so, who stops starting and helps finish?
  5. Close (1 minute). Confirm who is swarming on what, and note anything to raise at replenishment or the next review.

Detailed problem-solving does not belong in the meeting. When two people need to resolve something, agree that they will talk straight afterwards and move on.

How it differs from a Daily Scrum

The 2020 Scrum Guide defines the Daily Scrum as a 15-minute event for the Developers to inspect progress toward the Sprint Goal and adapt the Sprint Backlog, and lets them choose its structure. A Kanban meeting has no Sprint Goal to inspect against; its reference points are WIP limits, item age and the SLE. Because the Scrum Guide leaves the format to the Developers, a Scrum team may walk its board too, so in practice the two can look alike. See the Daily Scrum guide for the Scrum event.

Replenishment and delivery planning

These two cadences answer different questions and Kanban University keeps them separate on purpose. Replenishment decides which options the team commits to start, moving them across the commitment point. Delivery planning decides when finished work is handed over to customers and what must be ready for that handover. Committing to start work and committing to a delivery date are different promises.

Replenishment meetingDelivery planning meeting
DecisionWhat enters the system nextWhat leaves the system in the next delivery
TriggerWeekly, or when the Ready queue runs lowEach release window or customer handover
InputsFree capacity, priorities, cost of delay, classes of serviceItems that are done or nearly done, release constraints, customer readiness
OutputsA refilled, limited Ready queueA delivery plan, communications and any rollback arrangements

Teams that deploy continuously may hardly need a delivery planning meeting, because every finished item is released on its own. Teams with release trains, regulated sign-off or customer training usually do. For a full replenishment agenda, prioritisation with classes of service and a worked replenishment example, read our guide to Kanban planning.

The service delivery review

The service delivery review (SDR) is a regular review of how well a service is meeting its customers' expectations, using data rather than impressions. The Kanban University glossary describes reviews as cadences designed to reflect on the performance or risk of one or more services, and Anderson's 2015 article describes a client holding its SDR fortnightly.

It is the cadence that most clearly separates the Kanban Method from "a board with a stand-up". The daily meeting looks at individual items; the SDR looks at the service as a whole and asks whether customers are getting what they were led to expect.

Inputs and agenda

  • Delivery against expectation: share of items finished within the SLE, and the 85th percentile cycle time for the period.
  • Throughput: items finished per week, by work type or class of service. See throughput.
  • Ageing and blocked work: items older than the SLE and total blocked time.
  • Customer feedback: complaints, escalations, quality problems found after delivery.
  • Policies: are WIP limits, classes of service and the commitment point still right?
  • Outputs: agreed actions, policy changes to test, and items to pass to the risk or operations review.

Worked example: a fortnightly service delivery review

Illustrative example. An internal IT service team handles access requests, small changes and vendor-supported fixes. Its published SLE is "85% of standard items finished within 10 days" (calendar days, from the commitment point to done). In the last fortnight it finished 18 items with these cycle times, in days: 2, 3, 3, 4, 4, 5, 5, 6, 6, 7, 7, 8, 9, 9, 11, 12, 14 and 16.

MeasureCalculationResult
Throughput18 items ÷ 2 weeks9 items per week
Items within SLECount of cycle times of 10 days or less14 of 18
SLE attainment14 ÷ 18 × 10077.8%, below the 85% expectation
Items needed to meet 85%0.85 × 18 = 15.3, rounded up16 of 18
85th percentile this fortnightValue at rank 0.85 × 18 = 15.3, rounded up to 16, in the sorted list12 days, against an SLE of 10
Ageing work nowCurrent item ages: 1, 2, 2, 3, 5, 6, 8, 11, 13 days2 of 9 in-progress items already past the SLE

Interpretation. The service missed its expectation by two items in this fortnight, and two current items will add to next period's misses. Eighteen items is a small sample, so one bad fortnight is not proof that the SLE is wrong. The more useful question is whether the four late items share a cause. At the review, the team finds that three of the four waited for the same external vendor.

Decisions. The review agrees three actions: flag vendor-dependent items at the commitment point so their wait is visible from day one; pass the vendor delay to the monthly risk review for blocker clustering; and consider a separate SLE for vendor-dependent work if the pattern continues, so that customers of standard requests get an honest expectation. The team does not lower its WIP limits or change the SLE on the strength of one fortnight.

The team retrospective

Kanban teams improve continuously, but most still benefit from a regular, protected time to reflect. The Official Guide suggests a team retrospective every two weeks or monthly. The format can borrow from Scrum, but the agenda is driven by flow data rather than a Sprint: cycle time trends, the cumulative flow diagram, blocker patterns and the results of the last experiment.

Treat each agreed change as an experiment: state what you expect to change, how you will measure it and when you will review it. A retrospective that produces one tested policy change is more useful than one that produces ten good intentions. The Sprint Retrospective guide has facilitation techniques that work equally well here.

Risk, operations and strategy reviews

These three cadences operate above a single team. Most organisations reach them only when several teams or services depend on each other, and they often map onto meetings that already exist, such as a monthly operations meeting or a quarterly business review.

Risk review

Anderson added the risk review in 2014, after Klaus Leopold formalised blocker clustering in 2013. Its purpose is to understand what is likely to stop the service delivering and to respond, for example by clustering past blockers by cause, agreeing how a type of risk should be handled, or assigning a class of service. A monthly rhythm is common. The blocker-clustering technique turns a pile of red stickers into a ranked list of causes with the blocked days each one cost.

Operations review

The operations review looks across services rather than inside one. Managers and representatives of interdependent teams review flow across the whole network, shared bottlenecks, capacity allocation between work types and dependencies that keep delaying each other. Typically monthly, it is where local improvements are checked against their effect on the system as a whole; a team that speeds up by pushing work onto a downstream team has not improved the network.

Strategy review

The strategy review, typically quarterly, asks whether the organisation is offering the right services to the right customers and whether those services remain fit for purpose as the market changes. It sets direction and capacity allocation that the replenishment meetings then apply. In many organisations an existing quarterly planning or portfolio meeting can serve, as long as it uses delivery data from the operations and service delivery reviews. For the portfolio view, see agile portfolio management.

How the cadences connect

The cadences form a network of feedback loops, each feeding information up or decisions down. Anderson's 2015 article describes this information flow: replenishment output goes to the daily meeting, and the service delivery and operations reviews supply capability information to the strategy review.

  1. Strategy review sets direction and how capacity is shared between services and work types.
  2. Operations review turns that into cross-service decisions and checks the network's performance.
  3. Service delivery review checks each service against its customers' expectations and adjusts policies.
  4. Risk review looks for recurring causes of delay and feeds responses into policies and classes of service.
  5. Replenishment selects work to start within those priorities and policies.
  6. Daily Kanban meeting manages the flow of committed work.
  7. Delivery planning hands finished work over to customers.

Data flows the other way: cycle times, throughput and blockers recorded at the board feed the service delivery review; its findings feed the operations and strategy reviews. If a higher-level review is not using data from the board, it is disconnected from the work it is meant to steer.

How to choose and introduce your cadences

  1. List the meetings you already hold. Note each one's purpose, attendees and frequency. Kanban University expects you to adapt these rather than add seven new meetings.
  2. Map each existing meeting to a cadence. A weekly team meeting may become replenishment; a monthly management meeting may become the operations review.
  3. Start with the daily meeting and replenishment. Set them at the board, with a time-box, and run them for at least a month before adding more.
  4. Add a service delivery review once you have data. You need recorded start and finish dates and an SLE before the review can compare delivery with expectations.
  5. Combine cadences on small teams. Anderson describes a client that merged its fortnightly service delivery review into its weekly replenishment meeting, extending the meeting by 30 minutes every other week because the audience was the same.
  6. Add risk, operations and strategy reviews when several services interact. Their value grows with the number of dependencies.
  7. Review the cadences themselves. At a retrospective, ask whether each meeting produced decisions. Drop or merge any that only share information.

Worked example: a cadence calendar and its cost

Illustrative example. The IT service team from the service delivery review above has six people and a team lead. It works roughly 7.5 hours a day, so a four-week month of 20 working days gives each person about 150 working hours. After three months of Kanban it settles on this calendar:

CadenceFrequency and lengthWho attendsHours per attendee per month
Daily Kanban meeting15 minutes, 20 daysWhole team15 × 20 ÷ 60 = 5.0
Replenishment30 minutes, weeklyTeam lead, one team member, two requesting managers30 × 4 ÷ 60 = 2.0
Service delivery review45 minutes, fortnightlyWhole team and two customer representatives45 × 2 ÷ 60 = 1.5
Team retrospective60 minutes, monthlyWhole team1.0
Risk review45 minutes, monthlyTeam lead with other service leads0.75
Operations review60 minutes, monthlyTeam lead with other service leads1.0
Strategy review2 hours, quarterlyTeam lead and department head120 ÷ 3 ÷ 60 ≈ 0.67

Result. A typical team member attends the daily meeting, the service delivery review and the retrospective: 5.0 + 1.5 + 1.0 = 7.5 hours a month, or 5.0% of 150 working hours. The team member who also attends replenishment spends 9.5 hours (6.3%). The team lead, who attends every cadence, spends about 11.9 hours (7.9%).

What the team does with this. The calculation makes the cost of coordination visible and gives the team a basis for pruning. It also shows where the effort goes: two-thirds of a typical member's meeting time is the daily meeting, so keeping that meeting to 15 minutes matters more than trimming the monthly reviews. The figures assume full attendance and no overruns; a daily meeting that habitually runs to 25 minutes adds over three hours per person per month.

Common mistakes with Kanban meetings

  • Running the daily meeting as a round of status reports. Walk the board instead and talk about items, blockers and age, not about who was busy.
  • Copying all seven cadences on day one. A single team does not need an operations or strategy review. Start with two or three and add only when a question is going unanswered.
  • Holding an SDR without data. Without start and finish dates there is nothing to compare with expectations, and the review becomes a discussion of opinions.
  • Merging replenishment and delivery planning by accident. Agreeing to start something is not a promise of a delivery date; keep the two decisions distinct even if they happen in one meeting.
  • Letting reviews end without decisions. Kanban University's own definition says feedback without action is not a feedback loop.
  • Never improving between meetings. The Kanban Guide's point is fair: an obviously broken policy can be fixed the day it is noticed.
  • Treating Kanban as having no meetings at all. Kanban has no prescribed meetings, but a team with no feedback loops has a board, not a Kanban system.

Templates and tools for Kanban meetings

Our free meeting agenda template has columns for time, minutes, agenda item, owner, desired outcome and pre-reading, which suits the time-boxed agendas above. Record decisions and actions from reviews in the meeting notes template, which keeps decisions and owned actions in their own columns. The Kanban board template records start and finish dates on its Cards tab and calculates cycle time, giving you the data a service delivery review needs.

Digital boards can cut preparation time: Jira, for example, supports WIP limits on Kanban boards and includes cumulative flow diagrams and control charts for cycle time, which covers much of what a service delivery review needs. To decide which metrics to bring to each review, read Kanban metrics, and for a side-by-side comparison with Scrum's events, see Kanban vs Scrum.

Free templates for this topic

Browse all templates

Frequently asked questions

What are the ceremonies in Kanban?

Kanban has no mandatory ceremonies. The Kanban Method describes seven cadences: the daily Kanban meeting, replenishment, delivery planning, service delivery review, risk review, operations review and strategy review. Teams adopt only those they need.

Are Kanban meetings mandatory?

No. Kanban University recommends feedback loops but lets teams choose which cadences to hold and how often, and the Kanban Guide 2025.5 requires no meetings at all.

What is a cadence in Kanban?

A regular meeting or review that provides feedback on one or more services, such as a daily meeting or a fortnightly service delivery review. The feedback must lead to action to count as a feedback loop.

How long should a daily Kanban meeting be?

Lean Kanban's typical configuration is 10 to 20 minutes, and 15 minutes is a common time-box. None of the Kanban sources makes a length mandatory; keep it short by walking the board and taking detailed problem-solving offline.

What is the difference between a Kanban stand-up and a Daily Scrum?

A Kanban meeting reviews the flow of items against WIP limits, item age and the SLE. The Daily Scrum inspects progress toward the Sprint Goal and adapts the Sprint Backlog. Both are often run as a board walk.

Can Kanban cadences be combined?

Yes, and on small teams they usually should be. Anderson describes a client that folded its fortnightly service delivery review into its weekly replenishment meeting by adding 30 minutes every other week, because the same people attended both.

What happens in a service delivery review?

The service owner, team and customer representatives compare delivery with expectations, using measures such as SLE attainment, cycle time percentiles, throughput, ageing items and customer feedback, then agree policy changes or actions.

Do Kanban teams hold retrospectives?

Many do. Kanban University's Official Guide suggests a team retrospective every two weeks or monthly, focused on flow data and experiments.

What is a risk review in Kanban?

A regular review, often monthly, of what is likely to stop the service delivering. It commonly uses blocker clustering to rank causes of delay and agrees responses such as new policies or classes of service.

Who attends a Kanban strategy review?

Senior leaders and service owners, usually quarterly, to decide which services and types of work the organisation should focus on, informed by data from the operations and service delivery reviews.

Which Kanban meetings should a new team start with?

A daily Kanban meeting and a replenishment meeting, ideally adapted from meetings the team already holds. Add a service delivery review once you have cycle time data, and higher-level reviews when several services interact.

How much time do Kanban meetings take?

It depends on the calendar you choose. In the illustrative example in this guide, a team member spends about 7.5 hours a month, or 5% of working time, in a daily meeting, a fortnightly SDR and a monthly retrospective.