Project Forecasting: Methods, Examples and Steps
Project forecasting is predicting where a project will finish, mainly its final cost and completion date, from its performance so far and the work still to do. A good forecast gives the sponsor an honest, early warning while there is still time to act, and it is usually best stated as a range with a level of confidence rather than a single number.
Key takeaways
- Forecast both the final cost (EAC) and the completion date; one without the other gives a misleading picture.
- Earned value formulas such as EAC = BAC / CPI are a quick, objective starting point, not the final answer.
- Earned schedule (forecast duration = planned duration / SPI(t)) gives a time forecast that stays reliable late in the project.
- Monte Carlo simulation and Agile velocity ranges turn forecasts into probabilities and date ranges.
- Validate formula results with the team's re-estimate of remaining work, open risks and pending changes.
- Update forecasts every reporting period, track their accuracy and report them honestly.
What is project forecasting?
Project forecasting is the process of predicting a project's future outcomes, chiefly its final cost, completion date and resource needs, using actual performance to date, the remaining work and known risks. Unlike the original estimate, a forecast is updated throughout delivery, so decision makers always see the most likely end point compared with the approved baseline.
Forecasting is part of monitoring and controlling. In PMI's PMBOK Guide, eighth edition (November 2025), it sits within processes such as monitoring and controlling finances and the schedule.
Forecast, estimate, budget and target compared
These four words are often used loosely, which causes confusion in steering meetings.
| Term | What it is | When it is set | Can it change? |
|---|---|---|---|
| Estimate | A prediction of cost or duration made before the work is done | During planning, from the scope and assumptions | Refined during planning |
| Budget | The approved amount of money (the budget at completion, BAC) | When the cost baseline is approved | Only through formal change control |
| Forecast | The current best prediction of the final outcome, using actual performance | Every reporting period during delivery | Yes, every time it is updated |
| Target | A desired result, often a stretch goal set by management | Any time | At management's discretion |
The budget is a commitment; the forecast is a prediction. When the forecast moves away from the budget, the gap is a signal that needs a decision, such as a change in scope, extra funding or recovery actions. A forecast that is quietly adjusted to match the budget is no longer a forecast.
What to forecast
Most attention goes on cost and dates, but a complete forecast covers everything the sponsor needs to make decisions.
| Forecast item | Typical measure | Question it answers |
|---|---|---|
| Final cost | Estimate at completion (EAC) | What will the project cost in total? |
| Cost to finish | Estimate to complete (ETC = EAC - AC) | How much more money do we need? |
| Variance at completion | VAC = BAC - EAC | How far over or under budget will we finish? |
| Completion date | Forecast finish date or duration | When will the last deliverable be done? |
| Resource needs | People, skills or FTEs by month | Do we have the people for the remaining work? |
| Risk and contingency | Expected value of open risks; contingency remaining | Is the remaining contingency enough? |
| Benefits | Expected benefits and their timing | Is the project still worth doing? |
On large projects the forecast is usually produced at work package or control account level and then rolled up.
Project forecasting methods
Forecasting methods fall into two broad families. Qualitative methods rely on judgement and are used when there is little data, for example early in a project or for novel work. Quantitative methods use performance data and models and become more reliable as the project progresses.
| Method | Type | Data needed | Output | Best used |
|---|---|---|---|---|
| Expert judgement and team re-estimates | Qualitative | Knowledge of remaining work | Point or range estimate | Any time, especially after changes |
| Delphi technique | Qualitative | A panel of experts | Consensus range | Early, for uncertain work |
| Analogy and reference class forecasting | Qualitative / data-based | Outcomes of similar past projects | Adjusted estimate based on history | Business case and early planning |
| Earned value formulas | Quantitative | BAC, PV, EV, AC | EAC, ETC, VAC, TCPI | Once enough work is done for indices to settle |
| Earned schedule | Quantitative | PV curve, EV, actual time | Forecast duration | Throughout, including late in the project |
| Critical path update | Quantitative | Updated schedule network | Forecast finish and milestone dates | Every update on scheduled projects |
| Three-point estimates (PERT) | Quantitative | Optimistic, most likely, pessimistic durations | Expected value and spread | Re-estimating remaining tasks |
| Monte Carlo simulation | Quantitative | Ranges for durations, costs and risks | Probability of meeting dates and budgets | Large or high-risk projects |
| Velocity or throughput | Quantitative | Recent iteration data, remaining backlog | Date or scope range | Agile and flow-based work |
Qualitative methods
Expert judgement is the most used method of all, because someone has to decide whether the formula results make sense. The most valuable form is a structured re-estimate of the remaining work by the people doing it. The Delphi technique gathers anonymous estimates from a panel over several rounds, sharing the results between rounds until the range narrows.
Reference class forecasting starts from the actual outcomes of a group of similar past projects rather than from the details of this one. The idea comes from Daniel Kahneman and Amos Tversky's work on the planning fallacy and has been applied to projects by Bent Flyvbjerg and others. It is a strong check on optimism bias, especially in business cases.
Quantitative methods
Quantitative methods use the project's own data: earned value and earned schedule project indices forward, a schedule update recalculates the critical path, and Monte Carlo simulation and velocity ranges add a measure of uncertainty. The sections below work through each with numbers.
Forecasting cost with earned value
Earned value management (EVM) is the most widely used quantitative method for cost forecasting. It compares three numbers at each status date: planned value (PV), earned value (EV) and actual cost (AC), and derives the cost performance index (CPI = EV / AC) and the schedule performance index (SPI = EV / PV).
| Formula | Assumption | Use when |
|---|---|---|
| EAC = BAC / CPI | Current cost efficiency continues | The cause of the overrun affects the remaining work |
| EAC = AC + (BAC - EV) | Remaining work goes to the original budget | The variance was a one-off and the cause has gone |
| EAC = AC + (BAC - EV) / (CPI x SPI) | Cost and schedule performance both affect the remaining work | You are late and must still meet a fixed end date |
| EAC = AC + bottom-up ETC | The original estimates no longer apply | Scope, rates or approach have changed |
| ETC = EAC - AC | Cost of the remaining work | |
| VAC = BAC - EAC | Expected overrun (negative) or underrun | |
| TCPI = (BAC - EV) / (BAC - AC) | Efficiency needed on the rest of the work to finish on budget |
Worked example: forecasting final cost
A software implementation has a budget (BAC) of $200,000 and a planned duration of eight months. At the end of month four the figures are: PV = $80,000, EV = $70,000, AC = $85,000. So CPI = 70,000 / 85,000 = 0.824 and SPI = 70,000 / 80,000 = 0.875. The project is over budget and behind schedule.
| Forecast | Calculation | EAC | VAC |
|---|---|---|---|
| EAC (CPI continues) | 200,000 / 0.824 | $242,857 | -$42,857 |
| EAC (one-off variance) | 85,000 + (200,000 - 70,000) | $215,000 | -$15,000 |
| EAC (CPI x SPI) | 85,000 + 130,000 / (0.824 x 0.875) | $265,408 | -$65,408 |
| EAC (bottom-up) | 85,000 + team's ETC of $150,000 | $235,000 | -$35,000 |
The formulas give a range of roughly $215,000 to $265,000. To pick a figure, the project manager asks why the overrun happened. Here, the team found that integration work was harder than estimated and that this will affect the remaining interfaces, so the one-off formula is too optimistic. The team's bottom-up re-estimate ($235,000) sits close to the CPI-based figure ($242,857), which gives confidence. The forecast reported to the sponsor is $235,000 to $245,000, most likely around $240,000, with ETC of about $155,000.
The to-complete performance index adds a reality check: TCPI = (200,000 - 70,000) / (200,000 - 85,000) = 1.13. To finish on budget, the team would have to deliver $1.13 of value for every dollar spent from now on, while it has managed $0.82 so far. That gap is too large to close by working harder, so the sponsor must choose between extra funding and reduced scope. For more detail on every formula, see our guide to estimate at completion.
Forecasting the completion date
Cost formulas say nothing directly about dates. There are three common ways to forecast completion; use at least two.
1. Update the schedule and critical path
Enter actual start and finish dates and the remaining duration of each in-progress task, then let the scheduling tool recalculate. The new finish date comes from the updated critical path, which shows which tasks are actually driving the end date. This is the most direct method and the one most sponsors understand. Its weakness is that it depends on honest remaining durations, ideally from three-point estimates.
2. Use SPI to scale the planned duration
A quick check is forecast duration = planned duration / SPI. In the example, 8 / 0.875 = 9.1 months. It is simple but has a known flaw: SPI is calculated in money, and it always drifts back to 1.0 as the project nears completion, because eventually all planned value is earned, even if the project is months late. Late in a project it stops being useful.
3. Use earned schedule
Earned schedule (ES), developed by Walt Lipke in 2003 and extended by Kym Henderson, fixes that flaw by measuring schedule performance in time rather than money. ES is the point in time at which the current EV *should* have been earned according to the baseline. The key formulas are:
- ES = C + (EV - PV at C) / (PV at C+1 - PV at C), where C is the last whole period in which planned value is less than or equal to EV.
- SPI(t) = ES / AT, where AT is the actual time elapsed.
- SV(t) = ES - AT, the schedule variance in time units.
- Forecast duration (IEAC(t)) = planned duration / SPI(t).
Continuing the example, the cumulative planned value by month is shown below.
| Month | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
|---|---|---|---|---|---|---|---|---|
| Cumulative PV ($000) | 10 | 28 | 50 | 80 | 112 | 145 | 175 | 200 |
- EV at month four is $70,000. Planned value passed $50,000 at the end of month three and reached $80,000 at the end of month four, so C = 3.
- ES = 3 + (70,000 - 50,000) / (80,000 - 50,000) = 3 + 0.67 = 3.67 months.
- SPI(t) = 3.67 / 4 = 0.917, and SV(t) = 3.67 - 4 = -0.33 months (about a week and a half behind).
- Forecast duration = 8 / 0.917 = 8.7 months.
So the date forecasts range from 8.7 months (earned schedule) to 9.1 months (simple SPI). The project manager then checks the critical path: if the delayed integration tasks are on it, the later figure is more realistic; if they have float, the earlier one may be. The reported forecast is a finish between mid-month nine and early month ten, alongside the cost range.
Probabilistic forecasting with Monte Carlo simulation
Monte Carlo simulation makes uncertainty visible. Instead of one duration or cost for each remaining task, you enter a range (optimistic, most likely and pessimistic), plus the probability and impact of key risks. The software recalculates the schedule and cost thousands of times, picking random values from each range, and plots the spread of results.
The output is a set of confidence levels, often called P-values. P50 means there is a 50% chance of finishing on or before that date or cost; P80 means an 80% chance. The table shows an illustrative result for the remaining work in the example project.
| Confidence level | Forecast finish (illustrative) | Forecast final cost (illustrative) |
|---|---|---|
| P10 | 8.6 months | $226,000 |
| P50 | 9.1 months | $239,000 |
| P80 | 9.6 months | $251,000 |
| P90 | 9.9 months | $258,000 |
Reading it: the most likely outcome is close to the deterministic forecast, but if the sponsor wants 80% confidence they should plan for 9.6 months and about $251,000. The difference between P50 and P80 is a reasoned basis for schedule and cost contingency. It also shows which tasks and risks drive the spread most.
Monte Carlo is only as good as its ranges: if they are too narrow, which is common, the results look precise and are wrong. Use historical data where you can, and link the model to the risk register so known risks are modelled explicitly.
Forecasting in Agile projects
Agile teams usually fix time and cost per iteration and forecast how much scope will be delivered by a date, or when a given scope will be done. The inputs are the remaining backlog and the team's recent delivery rate: velocity in story points or throughput in items per week.
Worked example: a release forecast from velocity
A Scrum team has 240 story points left in the release backlog and works in two-week sprints. Its velocity over the last six sprints was 28, 32, 25, 30, 35 and 30 points (average 30).
| Scenario | Velocity used | Sprints needed (240 / velocity) | Weeks |
|---|---|---|---|
| Optimistic (average of best three sprints) | 32.3 | 7.4, so 8 sprints | 16 |
| Average | 30 | 8 sprints | 16 |
| Pessimistic (average of worst three sprints) | 27.7 | 8.7, so 9 sprints | 18 |
| Worst observed sprint repeated | 25 | 9.6, so 10 sprints | 20 |
The team reports a forecast of 8 to 10 sprints (16 to 20 weeks), most likely 8 or 9. The forecast is updated after every sprint, and the release burn-up chart shows both the completed work and any growth in scope, so the sponsor can see whether a slipping date is caused by slower delivery or by new backlog items.
Throughput and Monte Carlo for flow-based teams
Kanban teams often forecast from throughput instead. A simple Monte Carlo approach samples from the team's actual weekly throughput history to simulate thousands of possible futures, producing statements such as "85% chance of finishing these 60 items within 11 weeks". It needs no item estimates, only a reasonable history of completed work.
Resource and benefits forecasting
Resource forecasting predicts the people, skills and equipment the remaining work will need and when. Start from the updated schedule and ETC, convert the remaining effort into hours or FTEs by month for each role, and compare it with what is available. Gaps show where you need to hire, borrow or re-sequence work; see capacity planning.
Benefits forecasting asks whether the project will still deliver the value in its business case: a later finish delays benefits, an overrun reduces the return and scope cuts may remove benefits altogether. Revisit it at each phase gate.
How to produce a project forecast step by step
- Set the status date. Use the same cut-off date for progress, costs and risks so the figures are consistent.
- Check the data. Make sure actual costs include accruals and committed costs for completed work, and that progress is measured with agreed rules rather than optimistic percentages.
- Calculate the indicators. Work out CPI, SPI, SPI(t) and the formula-based EACs and durations. These take minutes in a spreadsheet.
- Update the schedule. Enter actuals and remaining durations and recalculate the critical path.
- Re-estimate the remaining work. Ask the people doing the work for a bottom-up ETC on work packages that have changed or are performing differently from plan.
- Add risks and changes. Include the expected cost of open risks, the remaining contingency, approved changes and change requests likely to be approved.
- Compare and choose. Put the formula results, the schedule update and the bottom-up estimate side by side, decide which is most credible and explain why.
- Express a range. State a most likely value and a range, with a confidence level where you have run a simulation.
- Report and act. Present the forecast, its drivers and the options to improve it, and record the forecast so you can compare it with the actual outcome later.
Steps 1 to 4 can largely be automated, leaving time for the judgement in steps 5 to 9, which is where forecasts become credible.
Choosing the right forecasting method
| Situation | Recommended methods |
|---|---|
| Business case or early planning, little project data | Reference class forecasting, analogy, expert judgement, three-point estimates |
| Less than about 15-20% complete | Bottom-up re-estimate and schedule update; treat earned value indices as early indicators only |
| Mid-project with stable performance | Earned value EACs and earned schedule, cross-checked with the critical path |
| After a major change or replan | Bottom-up ETC from the new plan; earned value from the new baseline |
| Late in the project | Earned schedule and critical path for dates (not simple SPI); bottom-up ETC for remaining items |
| Large, high-risk or contractual projects | Monte Carlo simulation on cost and schedule, alongside earned value |
| Agile or flow-based delivery | Velocity or throughput ranges, burn-up charts, throughput Monte Carlo |
Whatever the situation, use at least two independent methods. When they disagree, the difference tells you something important.
How to present a forecast
A forecast only helps if the sponsor understands it and can act on it. A clear forecast section in the project status report usually includes:
- Headline: the most likely final cost and finish date, compared with the baseline.
- Range and confidence: for example "$235,000 to $245,000; finish between mid-month nine and early month ten".
- Change since last report: what moved and why.
- Drivers: the two or three main causes of variance.
- Options: actions that would improve the outcome, with their cost and effect, such as reducing scope, adding people or using contingency.
- Decision needed: what you are asking the sponsor to decide, and by when.
Agree thresholds in advance, for example escalate if EAC exceeds BAC by more than 5% or the forecast finish slips past a key milestone, so a worsening forecast triggers a decision rather than a discussion. Our contingency plan guide explains how to set and release reserves when a forecast shows they are needed.
How accurate are project forecasts?
Forecasts become more accurate as the project progresses, because more of the cost is actual rather than estimated. There is some research evidence on how quickly earned value forecasts settle. In a 1993 study of 155 US Department of Defense contracts, David Christensen and Scott Heise found that once a contract was more than 50% complete, the cumulative CPI did not change by more than 10%. Later research, such as Henderson and Zwikael's work on performance stability, has questioned how far this applies to other kinds of project, so treat it as a useful guide rather than a rule.
The practical lesson: a project over budget at the halfway point rarely recovers without a specific change in how the remaining work is done.
Track your own forecast accuracy
Record each period's forecast of final cost and finish date, then compare them with the actual outcome at closure. A simple chart of forecast EAC over time shows whether forecasts were stable, drifted steadily upwards (a sign of optimism) or jumped late (a sign that problems were hidden). Capture the findings in your lessons learned so the next project's estimates and forecasts improve.
Common forecasting mistakes
- Forecasting what the sponsor wants to hear. Political pressure is the biggest single threat to an honest forecast.
- Assuming the project will recover without a concrete reason, such as a changed approach or added resources.
- Defaulting to the most optimistic formula. AC + (BAC - EV) gives the smallest number when you are over budget, but it assumes the problem has gone away.
- Forecasting cost without dates, or dates without cost. A late project nearly always costs more.
- Ignoring committed costs and accruals, which makes the project look cheaper than it is.
- Relying on inflated progress. If tasks sit at 90% complete for weeks, EV is overstated and every forecast is too rosy.
- Using simple SPI late in the project, when it drifts to 1.0 regardless of actual delay. Use earned schedule or the critical path.
- Reporting a single precise figure such as $242,857, which implies false certainty.
- Updating too rarely, so the forecast jumps near the end.
- Leaving out risks and pending changes that everyone on the team knows about.
Forecasting tools and templates
A spreadsheet is enough for earned value and earned schedule forecasting on most projects: you need the time-phased baseline, actual costs, progress by work package and a few formulas. Our free budget template tracks budget against actuals and forecast, and the release plan template supports velocity-based release forecasting for Agile teams. For the estimates behind your ETC, use the project cost estimate template.
Scheduling tools update forecast finish dates automatically, and Monte Carlo analysis can be run with a risk-analysis add-in or a spreadsheet simulation. Our comparison of project management tools shows which platforms offer Gantt charts, workload and reporting features.
Free templates for this topic
Frequently asked questions
What is project forecasting?
Predicting a project's final cost, completion date, resource needs and other outcomes from its performance to date and the work remaining, and updating that prediction throughout delivery.
What are the main project forecasting methods?
Expert judgement and bottom-up re-estimates, reference class forecasting, earned value formulas, earned schedule, critical path updates, three-point estimates, Monte Carlo simulation, and velocity or throughput forecasting for Agile teams.
How do you forecast the final cost of a project?
Calculate estimate at completion with earned value formulas such as EAC = BAC / CPI, then cross-check with a bottom-up estimate of the remaining work plus open risks and pending changes.
How do you forecast a project's completion date?
Update the schedule and critical path with actual progress, and cross-check with earned schedule: forecast duration = planned duration / SPI(t).
What is the difference between a forecast and an estimate?
An estimate is made before the work starts, from the scope and assumptions. A forecast updates the prediction during delivery using actual performance.
What is the difference between a forecast and a budget?
The budget is the approved amount and changes only through change control. The forecast is the current best prediction of the final cost and can change every period.
What is ETC in project forecasting?
Estimate to complete: the expected cost of the remaining work. ETC = EAC - AC, or a fresh bottom-up estimate of the remaining work.
What is earned schedule?
A method, developed by Walt Lipke, that measures schedule performance in time rather than money. It gives SPI(t) = ES / AT and a forecast duration of planned duration / SPI(t), and stays reliable late in a project.
What is a Monte Carlo project forecast?
A simulation that recalculates the schedule and cost thousands of times using ranges for each estimate and risk, showing the probability of finishing by a date or within a cost, such as P50 and P80.
How do Agile teams forecast?
By dividing the remaining backlog by a range of recent velocities or throughput, giving a date range, and updating it every iteration with a burn-up chart.
How often should project forecasts be updated?
Every reporting period, often monthly or every sprint, and whenever a significant change, issue or risk occurs.
Why should a forecast be a range rather than a single figure?
Because the future is uncertain. A range with a confidence level is more honest and helps sponsors set sensible contingency.
When are earned value forecasts reliable?
They become more reliable as the project progresses. Christensen and Heise's 1993 study of US defence contracts found the cumulative CPI changed by no more than 10% once contracts were over 50% complete, though later research questions how widely that applies.