S-Curve in Project Management: What It Is and How to Use It

An S-curve is a graph of cumulative cost, effort or progress plotted against time. It usually forms an S shape because spending starts slowly, speeds up in the middle of a project and tails off near the end. Comparing planned and actual S-curves shows at a glance whether a project is on track.

Key takeaways

  • An S-curve plots cumulative cost or work over time.
  • The baseline PV curve ends at BAC.
  • Compare EV with PV for schedule and EV with AC for cost.
  • Diverging curves are an early warning sign.

Why the curve is S-shaped

  • Start: few people, planning and design work, so cumulative cost rises slowly.
  • Middle: the full team and most purchases, so the curve is steepest.
  • End: testing, handover and closure with fewer people, so it flattens out.

How to build a baseline S-curve

  1. Create the schedule and assign a budget to each activity or work package.
  2. Total the planned cost for each period (week or month).
  3. Calculate the running cumulative total.
  4. Plot cumulative planned value against time. The last point equals the budget at completion.
  5. Each reporting period, add cumulative earned value (EV) and actual cost (AC) lines.

Example

MonthPlanned in monthCumulative PVCumulative EVCumulative AC
1$10,000$10,000$8,000$10,000
2$15,000$25,000$22,000$27,000
3$25,000$50,000$45,000$55,000
4$30,000$80,000$70,000$85,000
5$40,000$120,000
6$35,000$155,000
7$25,000$180,000
8$20,000$200,000

At month four the AC line ($85,000) sits above the EV line ($70,000): the project is over budget. The EV line sits below the PV line ($80,000): it is behind schedule. The gaps are the cost variance (-$15,000) and schedule variance (-$10,000).

How to read the three curves

PatternMeaning
EV below PVBehind schedule
EV above PVAhead of schedule
AC above EVOver budget for work done
AC below EVUnder budget for work done
Curves diverging over timeThe problem is growing; act now

Other uses of S-curves

  • Cumulative labour hours for capacity planning.
  • Cash-flow and funding requirements for the finance team.
  • Cumulative tasks or deliverables completed.
  • Target, early-start and late-start curves to show the range of possible spending profiles.

Tips

  • Plot the lines on the same axes and scale.
  • Extend the curve with a forecast line from today to the EAC.
  • Do not judge progress by the AC line alone; spending is not progress.
  • Most project management software and spreadsheets can produce S-curves.

Free templates for this topic

Browse all templates

Frequently asked questions

What is an S-curve in project management?

A graph of cumulative cost, effort or progress against time, which usually has an S shape.

Why is it called an S-curve?

Because cumulative spending starts slowly, accelerates mid-project and slows at the end, forming an S.

What does an S-curve show?

Planned versus actual progress and cost over time, making cost and schedule variances visible.

How do you create an S-curve?

Total the planned cost per period, calculate the running cumulative total and plot it against time.

What is a baseline S-curve?

The cumulative planned value curve from the approved cost baseline. It ends at BAC.

How is an S-curve used in earned value management?

PV, EV and AC are plotted as three cumulative curves; the gaps show schedule and cost variances.

What does it mean if the actual S-curve is above the plan?

If AC is above EV, the project is over budget for the work done. Compare AC with EV, not PV.

Can an S-curve be made in Excel?

Yes. Put periods in one column and cumulative values in others, then insert a line chart.

Does every project follow an S-curve?

Not always. Projects with large early purchases or a flat staffing profile may produce different shapes.

What is the end point of the baseline S-curve?

The budget at completion, the total planned cost of the work.