Change Request Template (Free Form and Change Log)

This free change request template gives you two things in one file: a one-page change request form to describe a proposed change and its impact, and a change log that records every request, its decision and who approved it. Download it for Google Sheets, Excel or PDF, in a beginner, advanced or expert version.

change request template

Key takeaways

Free download · no sign-up

Get the change request template

Pick your level and format: Google Sheets, Excel or a print-ready PDF. Spreadsheets include dropdowns, formulas and sample rows you can overwrite.

Beginner

Essential columns only, one tab. Quick to fill in.

1 tab · 5 columns

AdvancedMost popular

The full template with every tab, dropdowns and formulas.

2 tabs · 12 columns

Expert

Adds a live dashboard, instructions, revision history and status colours.

2 data tabs + instructions, dashboard and revision history

What is a change request?

A change request is a formal proposal to modify something a project has already agreed, such as its scope, schedule, budget, a deliverable or a plan. It describes the change, explains why it is needed, sets out its impact on time, cost, quality and risk, and records whether the change was approved, rejected or deferred, and by whom.

The PMBOK Guide treats change requests as the input to integrated change control, and earlier editions group them into four kinds: corrective action (bringing performance back in line with the plan), preventive action (avoiding a future deviation), defect repair (fixing a product that does not meet requirements) and updates to project documents or plans.

The key word is *proposal*. Raising a change request does not mean the change will happen. It starts a short, visible process in which someone with the right authority looks at the impact and makes a decision. That process is what stops a project drifting into scope creep.

For the full process around the form, see our change control guide.

Change log preview

The first tab is the change log. The sample rows below show three typical requests at different stages; overwrite them with your own.

Change log
CR #Date raisedRaised byChange descriptionReasonImpact: scopeImpact: time (days)Impact: cost ($)PriorityDecisionApproved byDecision date
CR-00110 Feb 2026Sales leadAdd export to CSV on invoices pageCustomer requestsMinor addition32,400MediumApprovedSponsor12 Feb 2026
CR-00218 Feb 2026SecurityAdd multi-factor loginSecurity policyNew feature109,000HighApprovedSteering group24 Feb 2026
CR-0031 Mar 2026MarketingChange brand coloursRebrandDesign rework53,500LowDeferredSponsor4 Mar 2026

Sample rows are examples: replace them with your own.

What's in the change request template

The template is a spreadsheet with two tabs that work together. Use the Change request form to write up one change in detail, then add a one-line summary of it to the Change log so you can see every request, and the total impact, in one place.

  • Change log: CR #, Date raised, Raised by, Change description, Reason, Impact: scope, Impact: time (days), Impact: cost ($), Priority, Decision, Approved by, Decision date
  • Change request form: Field, Details

Change log tab

The change log has 12 columns: CR #, Date raised, Raised by, Change description, Reason, Impact: scope, Impact: time (days), Impact: cost ($), Priority, Decision, Approved by and Decision date. In the advanced and expert versions, Decision is a dropdown (Pending, Approved, Rejected, Deferred) and Priority is a dropdown (High, Medium, Low).

Change request form tab

The form is a simple two-column layout (Field and Details) with 12 fields: change request number, requested by and date, description of change, reason or benefit, options considered, impact on scope, impact on schedule, impact on cost, impact on quality and risk, recommendation, decision and conditions, and approved by and date. Use one form per change.

Which version should you download?

VersionWhat you getBest for
BeginnerOne tab with the essential log columns: CR #, Date raised, Raised by, Change description and DecisionSmall projects that just need a record of requests and decisions
AdvancedBoth tabs (change log and change request form) with all 12 log columns and the Decision and Priority dropdownsMost projects with a sponsor or client who approves changes
ExpertEverything in Advanced, plus an instructions tab, a dashboard that counts requests by priority and decision automatically, colour-coded decisions and priorities, and a revision history tabPMOs, client work and projects with a change control board

What to include in a change request

A good change request gives the approver enough information to decide without a long meeting. These are the fields in the template, what to write in each, and an example.

FieldWhat to writeExample
Change request numberA unique ID so the request can be referenced in the log, minutes and planCR-004
Requested by / dateWho raised it and whenHead of Sales, 3 March
Description of changeWhat would change, in one or two plain sentencesAdd a CSV export to the invoices page
Reason / benefitWhy it is needed and what happens if you do nothingThree key customers export invoices by hand each month
Options consideredAlternatives, including doing nothing or deferringDefer to phase 2; offer a manual export report
Impact on scopeWhat is added, removed or altered in the deliverablesNew export function and help page
Impact on scheduleExtra days and any effect on milestones or the critical path+3 days; launch date unchanged if approved this week
Impact on costExtra effort, purchases or fees$2,400 of developer time
Impact on quality and riskNew risks, testing needs or effects on other deliverablesExtra regression testing on invoices
RecommendationWhat the project manager advisesApprove, using contingency
Decision and conditionsApproved, rejected or deferred, with any conditionsApproved, provided launch date holds
Approved by / dateName and role of the decision-maker and the dateSponsor, 5 March

How to fill in the change request template

Follow these steps for each change. The whole cycle for a small change can take a day; a large one may need a change control board meeting.

  1. Give the request a number. Use the next CR # in the change log so every request can be traced.
  2. Describe the change and the reason. Keep it short and specific. Ask the requester for the business benefit and the date they need it by.
  3. List the options. Include doing nothing, deferring to a later phase, a smaller version, or swapping it for something already in scope.
  4. Assess the impact. Estimate the effect on scope, schedule, cost, quality and risk with the people who will do the work (see below).
  5. Make a recommendation. As project manager, say which option you advise and why.
  6. Log it and route it for a decision. Add the request to the change log with Decision set to Pending, then send the form to the approver or change control board according to your thresholds.
  7. Record the decision. Fill in Decision, Approved by and Decision date in both the form and the log.
  8. Update the plan and tell people. For approved changes, update the project baseline, schedule, budget and scope documents, then tell the team and stakeholders. Tell the requester the outcome of rejected and deferred changes too.

How to assess impact

Impact assessment is where most of the value of a change request lies. Work through these questions with the team members who would do the work:

  • Scope: Which deliverables or work packages change? Does anything need to be removed to make room? Check against your work breakdown structure.
  • Schedule: How many extra days of effort, and does the change touch the critical path or a fixed milestone?
  • Cost: What extra labour, materials, licences or supplier fees are needed? Can contingency cover it?
  • Quality: Does it need extra testing, review or sign-off? Could it affect other features?
  • Risk: Does it create new risks or change existing ones? Add any new risks to the risk register.

Change request example

Here is a completed form for the second sample row in the template, a request to add multi-factor login to a customer portal project.

FieldDetails
Change request numberCR-002
Requested by / dateSecurity team, 18 February 2026
Description of changeAdd multi-factor authentication to the customer portal login.
Reason / benefitRequired by the company security policy for systems that hold customer data.
Options considered1) Add now; 2) Launch without it and add in phase 2; 3) Use the existing single sign-on provider's built-in option.
Impact on scopeNew feature: second-factor enrolment, login step and recovery process.
Impact on schedule+10 days of development and testing.
Impact on cost$9,000
Impact on quality and riskReduces security risk; adds a support risk if users lose access, so a recovery process is needed.
RecommendationOption 1. Launching without it would breach policy.
Decision and conditionsApproved. Launch date moves by two weeks; sponsor to inform customers.
Approved by / dateSteering group, 24 February 2026

Notice that the decision goes to a steering group rather than the sponsor alone. At $9,000 and ten days, it is above the thresholds in the next section. CR-001 in the sample log, a smaller $2,400 change, was approved by the sponsor.

Who approves a change request?

The approver depends on the size of the change and on what your project governance says. Agree thresholds at the start of the project and write them into your project management plan or project charter, so nobody has to argue about who decides.

The table below is an example of how many teams set thresholds. The figures are illustrative; set your own based on the size of the project and the sponsor's appetite for risk.

Size of changeExample thresholdWho decides
SmallUnder 2 days and under $1,000, no effect on milestones or agreed deliverablesProject manager (log it and report it)
MediumUp to 10 days or up to $5,000, or any change to an agreed deliverableProject sponsor
LargeOver 10 days or over $5,000, or any change to a key milestone, contract or benefitChange control board or steering group
EmergencyUrgent fix to a live service or safety issueNamed emergency approver, with a full change request completed afterwards

A change control board (CCB) is a group, often the sponsor, the project manager, a client representative and a technical lead, that reviews larger changes together. A RACI matrix is a quick way to make these roles explicit.

Types of change requests

You will see change requests classified in two ways: by purpose (the PMBOK Guide's categories) and by urgency and risk (common in IT change management and many project teams).

TypeWhat it meansExample
Corrective actionBrings work back in line with the planAdd a second tester to recover a slipped test phase
Preventive actionReduces the chance of a future problemOrder long-lead hardware early
Defect repairFixes a product or component that does not meet requirementsRework a report that shows the wrong totals
UpdateChanges a plan or project documentRevise the communication plan after a reorganisation
StandardLow-risk, routine change with a pre-approved procedureAdd a user to a system
Normal / majorNeeds a full assessment and formal approvalAdd a new module to the scope
EmergencyMust happen quickly to fix an urgent problemPatch a security flaw in a live system

You do not need to use every category. Many teams add a Type column to the change log or simply use Priority to separate routine requests from those that need the board.

Change request vs change order vs change log

These terms are often used loosely. Here is how they relate.

TermWhat it isWhen it is used
Change requestA proposal to change scope, schedule, cost or another baseline, with its impactWhenever someone wants to change something already agreed
Change orderThe binding instruction or contract amendment issued after a change is approved, common in construction and client contractsAfter approval, when a contract or purchase order must change
Change logA register of every change request with its status and decisionThroughout the project, as an audit trail
Change controlThe process for raising, assessing, deciding and implementing changesDefined at the start; used for the whole project

Change control is also different from organisational change management, which is about helping people adopt a new way of working.

Change requests in Agile projects

In Scrum and other Agile approaches, most change is expected and handled through the backlog rather than a change request. New ideas go to the Product Backlog, and the Product Owner orders them against existing work. The Sprint Goal is protected during a sprint.

A change request still has a place in Agile work when the change affects something outside the team's control, for example:

  • A fixed-price contract or statement of work that defines scope or deliverables.
  • A fixed budget or release date that the sponsor has committed to.
  • Regulatory, security or contractual requirements.
  • Dependencies on other teams or suppliers.

In these cases a lightweight version of the template (often the beginner change log) gives you an audit trail without slowing the team down.

Common change request mistakes

  • Accepting changes verbally. A "quick favour" agreed in a meeting never reaches the plan. Log everything, however small.
  • Assessing cost but not schedule or risk. A cheap change can still push the critical path or add risk.
  • No agreed thresholds. Every change ends up with the sponsor, or none of them do.
  • Leaving decisions open. Requests stuck at Pending create uncertainty. Set a target decision time.
  • Not updating the baseline. Approved changes must flow into the schedule, budget and scope documents, or your progress reporting will be wrong.
  • Ignoring the cumulative effect. Review the total of approved changes, not just each one in isolation.
  • Forgetting to close the loop. Tell requesters the outcome, including rejected and deferred requests.

Frequently asked questions

What is a change request template?

A change request template is a ready-made form for describing a proposed change to a project, explaining why it is needed, assessing its impact on scope, schedule, cost, quality and risk, and recording the decision. This one also includes a change log that lists every request.

Is this change request template free?

Yes. The change request template is free to download in Google Sheets, Excel and PDF, with no sign-up.

What should a change request include?

At minimum: a reference number, who raised it and when, a description of the change, the reason or benefit, the options considered, the impact on scope, schedule, cost, quality and risk, a recommendation, and the decision with the approver and date.

How do I write a change request?

Describe the change in one or two plain sentences, explain the business reason, list the options including doing nothing, estimate the impact with the people who would do the work, make a recommendation and send it to the person who has authority to approve it.

Who approves a change request?

It depends on the size of the change and your governance. Small changes are often approved by the project manager, medium ones by the sponsor, and large ones by a change control board or steering group. Agree these thresholds at the start of the project.

What is a change log?

A change log is a register of every change request on a project, with its impact, decision, approver and date. It gives you an audit trail and shows the combined effect of all changes.

What is the difference between a change request and a change order?

A change request is a proposal that has not yet been approved. A change order is the binding instruction or contract amendment issued once a change is approved, and is common in construction and client work.

What are the types of change requests?

The PMBOK Guide groups them by purpose: corrective action, preventive action, defect repair and updates. Many teams also classify them by urgency and risk, such as standard, normal or major, and emergency changes.

What is a change control board?

A change control board is a group of people, often the sponsor, project manager, a client representative and a technical lead, who review and decide on larger change requests together.

Do Agile projects need change requests?

Most change in Agile projects goes through the Product Backlog, ordered by the Product Owner. A change request is still useful when a change affects a contract, fixed budget, release date or another team.

Can I use the change request template in Excel or Google Sheets?

Yes. Download the .xlsx file for Excel or make a copy in Google Sheets. The advanced and expert versions include dropdowns for Decision and Priority; the PDF is for printing and signing.

Should small changes go through a change request?

Yes, but with a lighter process. Log every change, even small ones, and let the project manager approve those below an agreed threshold. Small unlogged changes are the main cause of scope creep.

What happens after a change request is approved?

Update the project plan, schedule, budget and scope baseline, assign the new work, and tell the team and stakeholders. Record the decision and date in the change log.