Free Work Package Template with Example (Excel, Sheets, PDF)

This free work package template describes one piece of project work on a single page: its WBS code, scope, deliverables, tasks, owner, effort and cost estimates, dates, dependencies, risks, acceptance criteria and sign-off. Download it in Google Sheets, Excel or PDF at beginner, advanced or expert level, with a worked example and no sign-up.

work package template

Key takeaways

Free download · no sign-up

Get the work package template

Pick your level and format: Google Sheets, Excel or a print-ready PDF. Spreadsheets include dropdowns, formulas and sample rows you can overwrite.

Beginner

Essential columns only, one tab. Quick to fill in.

1 tab · 2 columns

AdvancedMost popular

The full template with every tab, dropdowns and formulas.

1 tab · 2 columns

Expert

Adds instructions and revision history.

1 data tab + instructions and revision history

What is a work package?

A work package is the work at the lowest level of a work breakdown structure (WBS). PMI's PMBOK Guide defines it as the work defined at the lowest level of the WBS for which cost and duration are estimated and managed. In practice it is a clearly bounded piece of work with one owner, a defined output and an agreed way to check that it is finished.

The WBS shows the whole hierarchy of deliverables. The work package description, which is what this template produces, zooms in on one box of that hierarchy and records everything the person doing the work needs to know: what is in scope, what they must deliver, roughly how long it will take and cost, what it depends on and how it will be accepted.

The work package owner (often a team lead, team manager or supplier) is accountable for delivering it. The project manager agrees and authorises the package, and an approver signs it off. On larger projects, work package descriptions are often collected into a WBS dictionary, which holds the detail for every element of the WBS.

For the concept in more depth, read our guide to what a work package is.

What is in this work package template

The template has one tab, Work package, laid out as a simple form with two columns: Field and Details. It comes with a worked example (a customer login feature) that you overwrite with your own work. Here is a live preview:

Work package
FieldDetails
WBS code1.4.2
Work package nameCustomer login and password reset
OwnerTech lead
Description / scopeBuild login, logout and password reset using single sign-on.
DeliverablesWorking feature in test environment; unit tests; release notes.
TasksDesign screens; build API; integrate SSO; write tests.

Sample rows are examples: replace them with your own.

  • Work package: Field, Details

The 13 fields

  • WBS code: the reference from your WBS, for example 1.4.2, so the package traces back to its parent deliverable.
  • Work package name: a short noun phrase that matches the WBS entry.
  • Owner: the one person accountable for delivering the package.
  • Description / scope: what the work covers, and where useful what it does not cover.
  • Deliverables: the outputs that will exist when the package is finished.
  • Tasks: the main activities needed to produce the deliverables.
  • Effort estimate (days): the total working days of effort, not elapsed time.
  • Cost estimate ($): labour plus any materials, equipment or services. Change the currency label if you work in another currency.
  • Start / finish: the planned dates from your schedule.
  • Dependencies: other packages, projects, suppliers or decisions this work relies on.
  • Acceptance criteria: the testable conditions the output must meet to be accepted.
  • Risks: the main threats to the package; record them in full in your risk register.
  • Approved by / date: who signed the package off and when.

Blank rows sit under the fields so you can add your own, such as budget code, tolerances or reporting frequency.

Beginner, advanced and expert versions

VersionWhat you getBest for
BeginnerThe one-tab work package form with all 13 fields, the worked example and extra blank rowsQuick, informal hand-overs
AdvancedThe same one-tab, 13-field form: the standard versionMost projects
ExpertThe work package form plus an Instructions tab (steps and tips) and a Revision history tab for version, date, author, changes and approverProjects with formal sign-off, audits or a PMO

Because the work package is a two-column form, the beginner and advanced versions contain the same fields. The template has no status column, so the expert version does not include a dashboard; track the status of all your packages in your WBS or project schedule template instead. The PDF is a print-ready copy for kick-off meetings and sign-off.

How to fill in the work package template

  1. Start from the WBS. Copy the WBS code and name from your work breakdown structure template. Write one work package description for each lowest-level element that needs one.
  2. Agree the owner. Name one person, not a team. Talk to them before you write the rest; they know the work better than you do.
  3. Describe the scope. Say what is included and, if there is room for doubt, what is excluded. Check it against your project scope statement.
  4. List the deliverables, then the tasks that produce them. Keep tasks at a level the owner recognises; the detailed task list can live in their own plan.
  5. Estimate effort and cost with the owner, using past data or effort estimation techniques such as analogous or three-point estimates.
  6. Add dates and dependencies from your schedule, and record anything outside the owner's control that the package relies on.
  7. Write acceptance criteria and risks. Make every criterion testable, and copy the significant risks to your risk register template.
  8. Agree and approve. Walk through the package with the owner and approver, then record the approval and date before work starts. After that, changes go through change control.

Spreadsheet tips

  • Duplicate the tab for each package and rename it with the WBS code (1.4.2, 1.4.3) so the tabs sort in WBS order.
  • Use the same units everywhere. If effort is in days on one package, do not switch to hours on the next; the totals will not add up.
  • Roll the numbers up. Copy each package's effort and cost into your project cost estimate template so the project budget is built from the bottom up.
  • Keep it to one page. If it runs longer, the package is probably too big.

Work package example

The template's sample package is a software feature, but the same structure works for a construction stage, a marketing campaign asset or a training course. Here is the example with a note on why each entry works:

FieldExample entryWhy it works
WBS code / name1.4.2 Customer login and password resetTraces directly to the WBS
OwnerTech leadOne accountable role (use a named person in your own file)
Description / scopeBuild login, logout and password reset using single sign-onShort and specific about what is in scope
DeliverablesWorking feature in test environment; unit tests; release notesOutputs you can see and check
TasksDesign screens; build API; integrate SSO; write testsEnough to estimate, not a full task list
Effort / cost12 days; 9,600Estimated by the person doing the work
Start / finish2 Mar 2026 / 17 Mar 2026About two weeks: easy to track
DependenciesSSO service (IT security project)Names an outside dependency to watch
Acceptance criteriaAll login test cases pass; security review approvedObjective pass or fail tests
RisksSSO delayLinked to the dependency; add it to the risk register

The approval field is blank in the example: fill it in only when the owner and approver have agreed the package.

How big should a work package be?

There is no fixed standard, but two rules of thumb are widely used:

  • The 8/80 rule: a package should take at least 8 hours and no more than 80 hours of effort. Smaller than that and you are managing tasks, not packages; larger and it becomes hard to estimate and track.
  • The reporting period rule: a package should be no longer than one reporting period (often two weeks or a month), so every status report shows it as either started, finished or clearly late.

Treat these as guides rather than limits; a large engineering project may hand a contractor packages of several hundred hours.

Signs you should split or merge a package

  • Split it if it has more than one owner, several unrelated deliverables, an estimate nobody is confident about or a duration longer than your reporting cycle.
  • Merge it if it is only a few hours of work, has no separate deliverable or would be tracked by the same person alongside its neighbour anyway.

Writing good acceptance criteria

Acceptance criteria turn "done" into something you can check. Write them so that the owner and approver would reach the same answer independently:

Weak criterionStronger criterion
Login works wellAll 24 login test cases pass in the test environment
SecureSecurity review completed and approved by the IT security lead
Documentation providedRelease notes published to the team wiki and reviewed by support
Wall built to standardWall inspected and signed off against drawing A-104 by the site engineer

Criteria can cover functionality, quality standards, documentation and approvals. For quality-critical work, link the criteria to your quality plan, and see our guide to project deliverables for how deliverables are accepted at project level.

Work packages in PRINCE2

In PRINCE2 a work package is a formal management product. Under the Controlling a Stage process, the project manager authorises a work package; under Managing Product Delivery, the team manager accepts it, agreeing that it is understood and achievable, and then delivers it. The team manager reports progress through checkpoint reports at the frequency set in the work package.

Our template covers the core of a work package description. To use it as a PRINCE2 work package, add rows for:

  • Product descriptions for the products to be delivered, including quality criteria
  • Tolerances for time and cost (and scope, risk or quality if you use them)
  • Reporting arrangements, including checkpoint frequency
  • Constraints and techniques or quality methods to be used
  • Problem handling and escalation: how issues and risks are raised to the project manager

Your organisation may have its own PRINCE2 format; if so, follow it.

Work packages in Agile projects

Agile teams rarely use the term work package, but the idea still applies. An epic or feature plays a similar role: a bounded chunk of value, broken down into smaller items and accepted against agreed criteria and the Definition of Done.

Where Agile and traditional teams work together, for example when a supplier delivers a fixed piece of work into an Agile programme, a one-page work package is a useful contract between them. For planning the Agile side, use our agile project plan template.

Work package vs task vs WBS

TermWhat it isTypical sizeOwned by
WBSThe full hierarchy of project deliverablesThe whole projectProject manager
Control accountA management point that groups work packages for cost and schedule control, used in earned value managementSeveral packagesControl account manager
Planning packageA WBS element with known scope but not yet detailed into work packagesVariesProject manager
Work packageThe lowest WBS level, estimated, scheduled and accepted as a unitDays to a few weeksWork package owner
Task or activityA step needed to complete a work packageHours to daysTeam member

Work packages describe what is delivered; tasks describe how it gets done. Tasks are what you sequence and resource in the schedule. Our guide to project tasks and activities explains the difference in more detail, and earned value management shows how control accounts and work packages are used to measure performance.

Common work package mistakes

  • No single owner. "Development team" is not an owner; name one person.
  • Scope that overlaps another package. Every piece of work should belong to exactly one package, or it gets done twice or not at all.
  • Estimates made without the owner. People commit to estimates they helped make.
  • Vague acceptance criteria. "To the client's satisfaction" invites disputes.
  • Hidden dependencies. If the package relies on another team, supplier or decision, write it down and track it in the schedule. See task dependencies.
  • Starting before approval. Without sign-off you have no agreed baseline to measure against.
  • Never updating it. If scope, dates or estimates change, record the change and a new version rather than editing silently.

Frequently asked questions

What is a work package template?

A work package template is a ready-made form for describing one work package: its WBS code, scope, deliverables, tasks, owner, effort and cost estimates, dates, dependencies, risks, acceptance criteria and approval.

Is this work package template free?

Yes. The work package template is free to download in Google Sheets, Excel and PDF, at beginner, advanced and expert level, with no sign-up.

What should a work package include?

At minimum: a WBS code and name, an owner, a description of scope, deliverables, effort and cost estimates, start and finish dates, dependencies and acceptance criteria. Many organisations add risks, tolerances, reporting arrangements and an approval record.

How big should a work package be?

A common rule of thumb is 8 to 80 hours of effort, or no longer than one reporting period. Larger projects sometimes use bigger packages; the test is whether one owner can estimate, track and deliver it.

What is the difference between a work package and a task?

A work package defines a deliverable-focused chunk of work at the lowest level of the WBS. Tasks or activities are the steps needed to complete it, and are what you schedule in detail.

What is the difference between a work package and a WBS?

The WBS is the whole hierarchy of project deliverables. A work package is one element at the bottom of that hierarchy, described in detail.

Who owns a work package?

One named work package owner, such as a team lead, team manager or supplier, is accountable for delivering it. The project manager agrees and authorises it.

Can I use this template as a PRINCE2 work package?

Yes, as a starting point. Add rows for product descriptions, tolerances, reporting arrangements, constraints, quality methods and problem handling, or follow your organisation's PRINCE2 format.

Is a work package the same as a WBS dictionary entry?

They are closely related. A WBS dictionary holds the detailed description of every WBS element; a work package description like this one is the entry for one lowest-level element, often with extra detail for authorising the work.

Can I use work packages in Agile projects?

Yes. Epics or features play a similar role, and a work package is useful when a supplier or traditional team delivers a defined piece of work into an Agile project.

How do I manage several work packages in one file?

Duplicate the Work package tab for each package and name each tab with its WBS code. Track the status of all packages in your WBS or project schedule.

What goes in the acceptance criteria of a work package?

Clear, testable conditions the output must meet, such as tests passed, standards met, documents delivered and approvals obtained.

What is the difference between the beginner, advanced and expert work package template?

All three contain the same one-tab, 13-field work package form with a worked example. The expert version adds an Instructions tab with steps and tips and a Revision history tab for recording versions and approvals.